Construction Web guide: infrastructure, buildings, engineering, architecture
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us

Federal Preemption
Developer's Claim for Indemnity Against Architect for ADA and FHA Violations Rejected

Not Like Private Deals
City Contract May Not Be Modified Orally or by Course of Dealing, Court Holds

Business Risk Exclusion
CGL Insurer that Refused to Defend, Pay Claim Penalized, Held Liable

Little Known Hazard
Plumbers Burned as a Result of Natural Gas 'Odor Fade,' but Damage Award Reversed

Could Apply Broadly
Design Professional Denied Protection of Contract's Liability Limit by Florida Court

Part Of Lung Removed
Contractor Escapes Liability When Plaintiff Cannot Tie Infectious Fungus to Jobsite Dirt Stockpile

Disgorgement Order
Court Allows Discharge in Bankruptcy of Penalty for Violation of Contractor Licensing Law

Obligations Discharged
When Surety Takes Over Project, Owner Cannot Object to Replacement Contractor, Court Holds

Default Judgment
Notice, Accident, Own Work Defenses Rejected in Claims by General Contractor Against Plumber's Insurer

Previous Issues

Construction Industry News

When Contractor and Subcontractor Start Construction but Cannot Agree on Subcontract, Idaho Supreme Court Implies an Agreement with 'Industry Standard' Provisions


November 25, 2002


Back to Industry Newsletters
 

(A revised version of this article appears in The Construction Lawyer, Volume 22, No. 4, Fall 2002, published by the American Bar Association's Forum on the Construction Industry.)


By John W. Ralls

Two contractors agreed to work together to submit a bid for a large fire alarm system installation project. The two agreed on a division of responsibility for the scope of work. They also agreed that one (an electrical contractor) would take the lead and that the other (a fire alarm contractor) would perform as a subcontractor. The bid was successful.

Work commenced before a written subcontract was signed. As work proceeded, there were a number of changes to the work, and the subcontractor performed a considerable amount of work at the direction of the prime.

The major sticking point in negotiations over the terms of the subcontract centered on the changes clause. The prime contractor favored a "flow-down" or "flow through" clause "whereby [subcontractor] would receive whatever compensation [owner] decided to pay" to the prime contractor for the changed work. The subcontractor favored a "bidding procedure" under which the subcontractor's estimates for the cost of changes would be treated as a series of fixed price contracts, a procedure the prime contractor found unacceptable.

The two were unable to resolve the issue. The subcontractor ended up walking off the project before it was completed, claiming that the prime contractor's failure to make timely payments excused the subcontractor's future performance. The prime contractor completed the project using another subcontractor.

The subcontractor sued the prime to recover the cost of its work. The prime counter-claimed to recover additional costs incurred in completing the work. The matter proceeded to a bench trial.

During the project, the owner required the prime contractor to submit estimates of the cost involved in any change order. The prime contractor requested pricing for changes, and the subcontractor provided the pricing. There was conflicting evidence at trial concerning the parties' intent with regard to the change order pricing submitted. The prime contractor contended the pricing was an estimate to be presented to the owner for approval. The subcontractor treated the pricing as a unilateral offer that was accepted when prime contractor instructed the subcontractor to proceed with the requested work.

The trial court concluded that the parties had an implied-in-fact contract entitling the subcontractor to payment for its work at reasonable rates. The trial court, largely adopting findings proposed by the prime contractor, also concluded:

"Because the parties never agreed about the procedures for change orders, but continued to work under the [prime] contract, the Court concludes that they had an implied in fact contract about the change orders. The parties intended to follow established government requirements for contract modifications known as the 'flow down' provision. The parties implemented this provision each time [subcontractor] presented estimates for additional work and negotiated a fair and equitable price with [prime contractor] and [owner]."

The trial court entered judgment in favor of the prime contractor. The subcontractor appealed. The Idaho Supreme Court affirmed. Fox v. Mountain West Elec., Inc., 2002 WL 1225091 (Idaho 2002).

Under Idaho law, an implied in fact contract exists when "there is no express agreement but the conduct of the parties implies an agreement from which an obligation in contract exists."

After noting that the trial court's findings are to be liberally construed in favor of the judgment entered, the Idaho Supreme Court found that the trial court's findings concerning the parties' conduct were supported by the evidence. "Using the [trial] court's findings that pricings submitted by [the subcontractor] were used by [the prime contractor] as estimates for the change orders, the conclusion made by the district court that an implied-in-fact contract allowed for the reasonable compensation of [the subcontractor] logically follows and is grounded in the law of Idaho."

The court noted that there was evidence presented at trial that the flow-down method of compensation was "industry standard" rather than the "series of fixed price contracts" method favored by subcontractor and that under Idaho law, a contractor is entitled to the reasonable value of additional services rendered.

The subcontractor also argued that the "gap filling" provisions of the Uniform Commercial Code should apply because the predominant factor of the transaction was the sale of components for the fire alarm system, not services. The subcontractor "argued that… various terms were agreed upon by the parties in the prior agreement drafts, including terms for the… payments" which, under the UCC, should be given effect. The trial court found that the contract contained both goods and services but that the predominant factor was services. The Idaho Supreme Court held there was no error in this finding.

The Idaho Supreme Court also affirmed the trial court's findings that the subcontractor breached the agreement by walking off the job and that the prime contractor was entitled to recover additional sums paid to the replacement contractor.


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.


Send This Report to a Colleague

Tools to Share, Organize, Comment on Information


©2002 ConstructionWebLinks, Inc.

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© ConstructionWebLinks, Inc.
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us