|
By
Paul W. Berning Three
recent bid protest decisions by the U.S. General Accounting Office illustrate
the importance of not waiting until the last minute when submitting electronic
bids to the federal government. Two protests were denied because the bids were
deemed to be untimely even though the bidders experienced problems or delays with
government electronic bidding systems. The third protest was sustained because
the electronic version of a bid was timely even though a duplicate paper bid was
late. Timely
Start Not Enough; Deadline Applies to Entire Bid
The
Department of Energy's Office of Classified and Controlled Information Review,
using its Web-based Industry Interactive Procurement System (IIPS), issued a request
for proposals for technical support services. The RFP required that responses
be submitted electronically and gave detailed instructions for their submission.
Responses were to be submitted in three volumes by noon (Eastern Standard Time)
on July 25, 2002, in Word, WordPerfect, Excel, Lotus 1-2-3 or PDF formats. PMTech,
Inc. began trying to submit its proposal at 11:46:38 a.m. on July 25, according
to a computer log from the IIPS system. At 11:47:27, PMTech attempted to submit
something, but an error occurred. A message, "SSL Handshake failed,"
was generated on the log. By noon, PMTech had managed to submit only the cover
sheet for its proposal. Its complete bid was not successfully submitted until
July 26. PMTech's bid was rejected as untimely, and it protested to the Comptroller
General of the United States, head of the GAO. The protest was denied. In re
PMTech, Inc., B-291082 (2002). PMTech
asserted that it took "all reasonable steps" necessary to submit its
bid timely and that it in fact timely uploaded material to the IIPS system. It
submitted a supporting statement from an "information technology scientist."
He reviewed IIPS' computer logs and concluded that errors within the IIPS system
prevented timely submission of the bid. The
GAO rejected PMTech's arguments. It began by reviewing basic Federal Acquisition
Regulation provisions and decisions governing timely submission of proposals:
Bidders are responsible for delivering their proposals to the proper place by
the proper time. Proposals received after the exact specified time are late. Proposals
are considered late even if some portions are submitted timely but if material
portions are received after the deadline. Late proposals generally may be considered
only if received before award of the contract and only if the circumstances satisfy
specific requirements set out in FAR. Acknowledging that the rule may "seem
harsh," the GAO noted that the rule alleviates confusion and prevents one
offeror from obtaining a competitive advantage. Regarding electronic bidding,
the GAO wrote: We
view it as an offeror's responsibility, when transmitting its proposal electronically,
to ensure the proposal's timely delivery by transmitting the proposal sufficiently
in advance of the time set for receipt of proposals to allow for timely receipt
by the agency.
The
GAO held that the primary cause of late delivery of PMTech's bid "was that
PMT delayed attempting to transmit its proposal until only 13 minutes" before
the deadline. The
GAO noted that PMTech based its protest on claims of computer errors in the IIPS
system. But, the GAO cited evidence that the system operated throughout July 25
and received a number of other bids for the RFP at issue and bids for other RFPs.
It noted that even PMTech did not claim the IIPS system was inadequate. Citing
prior decisions involving faxes, the GAO concluded that a bidder's obligation
to submit its bid timely included "allowing a reasonable amount of time for
the delivery of the proposal." Waiting until only 13 minutes before the deadline
was not reasonable, the GAO found. Noting that "[o]ccasional errors in computer
systems are a fact of life," the GAO concluded: We
think an offeror accepts the risk of late receipt and rejection of a proposal
where it delays transmitting its proposal until the last few minutes before the
time set for receipt of proposals.
Bid
Must Reach Final Destination Timely, Not Just Initial Point of Entry
The
GAO held that another bid - although received by the federal government's e-mail
system before the deadline - was untimely because it had not reached the
specified e-mailbox by the deadline. In re Sea Box, Inc., No. B-291056
(2002). The
RFP from the Army Material Command for equipment required that bids be received
by 1 p.m. in electronic format. They could be delivered by hand (on floppy disk
or CD-ROM, for example) or electronically (by e-mail or "datafax").
A particular e-mail address was specified in the RFP. The RFP also referenced
FAR §52-215-1. It makes bidders responsible for timely submissions and defines
as "late" any bid received after the specified time. It provides that
late bids can be considered only if received before the award is made; if the
contracting officers determines that considering them will not unduly delay the
acquisition; and: | | (1) | If
[the bid] was transmitted through an electronic commerce method authorized by
the solicitation, it was received at the initial point of entry to the Government
infrastructure not later than 5:00 p.m. one working day prior to the date specified
for receipt of proposals; or | | | | | | | (2) | There
is acceptable evidence to establish that it was received at the Government installation
designated for receipt of offers and was under the Government's control prior
to the time set for receipt of offers; or | | | | | | | (3) | It
is the only proposal received. |
The
GAO found that 11 minutes before the deadline, the bidder began sending the seven
e-mails that constituted its bid. All seven were received by the agency's initial
point of entry for e-mail, a mail relay host server, 8 to 10 minutes before the
deadline. However, the e-mails were held at the point of entry for 17 to 33 minutes,
then were sent to a virus scanning server, then were sent to a mail distribution
server and then, finally, were sent to the specified e-mailbox. The emails arrived
7 to 24 minutes late at the e-mailbox, and the agency rejected the bid as late. The
bidder conceded that it did not qualify for the first exception because its bid
was not electronically received by 5 p.m. the preceding day. But, it argued that
its bid should be accepted under the second exception because its entire bid had
arrived at the government's initial point of entry - and was out of the bidder's
control and was in the government's control -- before the deadline. That the government's
system then took time to process and relay the message to the designated e-mailbox
should not disqualify the proposal, the bidder argued. The
GAO rejected the argument. It held that the second exception for late bids applied
only to those delivered by non-electronic means. It held that the first exception
was the only one that applied to electronically delivered bids. To rule otherwise
would render the first exception a nullity, the GAO concluded. Late
Paper Bid Saved By Timely Electronic Bid
A
third protest was allowed when the bidder timely submitted its bid electronically
but was late submitting the paper version. In re Tishman Construction Corp.,
No. B-292097 (2003). The
RFP for construction management services from the Department of Health and Human
Services required bidders to submit their bids on paper and electronically. The
bids were to be identical. The RFP specified that the "paper copy is the
official copy for recording timely receipt of proposals." The electronic
version could be submitted online through the agency's CRON (Contracts Review
Online) system using PDF images or by CD-ROM or ZipDisk delivered by an express
service. The
protester's electronic bid was received in the required format through CRON 50
minutes before the 4 p.m. (Eastern Standard Time) deadline. But, the paper version
was delivered 73 minutes late. The agency rejected the bid as untimely. The
bidder argued that late delivery of the paper version of its bid was a minor informality
that should be disregarded because its electronic bid was timely and because it
was identical to the paper bid. The
GAO noted that FAR §15.208 provides that late bids generally should not be
considered and that the reason is to alleviate confusion, ensure equal treatment
of bidders and prevent the late bidder from obtaining a competitive disadvantage. But,
the GAO also noted a prior decision in which a bidder was required to submit its
bid at two locations but did so timely at only one location. The GAO held that
was only a minor informality because the agency had a complete copy of the bid
timely and no competitive advantage was obtained. In re Abt Associates, Inc.,
No. B-2276063 (1987). HHS
opposed the protest, citing another case in which the late bid was rejected. In
re Inland Service Corp., No. B-252947.4 (1993). But, the GAO pointed out that
in Inland Service, the bidder had failed to timely provide a complete copy
of its bid at any location. The
GAO sustained Tishman's protest because a complete copy of the bid was received
timely in a manner specified, no competitive advantage was obtained and no confusion
ensued. 1/ The
GAO never addressed the RFP's express provision that the paper version of the
bid rather than the electronic version was "the official copy for recording
timely receipt of proposals." If
you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.
ENDNOTE 1/ The agencies seeking bids are part of the Executive Branch of the federal government, and the GAO and Comptroller General are part of the Legislative Branch. Accordingly, the GAO cannot directly compel a federal agency to accept or reject a bid. If a bid protest is sustained by GAO, it generally will recommend a corrective action, which can include reimbursement of attorney fees. When GAO recommends a corrective action, the Competition in Contracting Act of 1984 (P.L. 98-369) requires the affected agency to report to the Comptroller General if the agency has not fully implemented the recommendation within 60 days. The Comptroller General, in turn, reports to Congress if a recommendation is not fully implemented. For more information on bid protests and procedures, click here.
©2003 ConstructionWebLinks, Inc.
|