Construction Web guide: infrastructure, buildings, engineering, architecture
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us

Federal Preemption
Developer's Claim for Indemnity Against Architect for ADA and FHA Violations Rejected

Not Like Private Deals
City Contract May Not Be Modified Orally or by Course of Dealing, Court Holds

Business Risk Exclusion
CGL Insurer that Refused to Defend, Pay Claim Penalized, Held Liable

Little Known Hazard
Plumbers Burned as a Result of Natural Gas 'Odor Fade,' but Damage Award Reversed

Could Apply Broadly
Design Professional Denied Protection of Contract's Liability Limit by Florida Court

Part Of Lung Removed
Contractor Escapes Liability When Plaintiff Cannot Tie Infectious Fungus to Jobsite Dirt Stockpile

Disgorgement Order
Court Allows Discharge in Bankruptcy of Penalty for Violation of Contractor Licensing Law

Obligations Discharged
When Surety Takes Over Project, Owner Cannot Object to Replacement Contractor, Court Holds

Default Judgment
Notice, Accident, Own Work Defenses Rejected in Claims by General Contractor Against Plumber's Insurer

Previous Issues

Construction Industry News

New Jersey Contractor Avoids Loss from Unbalanced Bid


October 14, 2002


Back to Industry Newsletters
 

ConstructionWebLinks.com

A recent decision by the New Jersey Supreme Court illustrates the perils a contractor faces if it submits an unbalanced or front-end loaded bid for a construction project. M.J. Paquet v. New Jersey Department of Transportation, 171 N.J. 378, 794 A.2d 141 (N.J. 2002). The court explained that when a construction bid is unbalanced because it contains below market prices for some work and inflated prices for other work, the contractor faces the risk of losing out if the inflated bid items are deleted by change order. The court nevertheless found that because of some unique facts in the case, the contractor was entitled to recoup the losses it incurred because of its unbalanced bid.


Facts

In October 1992, the New Jersey Department of Transportation solicited bids to rehabilitate several highways, including painting 12 bridges in northern New Jersey. The specifications required bidders to estimate the cost, overhead and anticipated profit for each pay item of work, with the contract being awarded to the overall low bidder. The bid specifications required that the bidding contractors submit "balanced bids" and further specified that NJDOT would "not consider any claim for additional compensation arising from the bid on an item, or group of items, inaccurately reflecting the cost of such work or containing a disproportionate share of the bidder's anticipated profit, overhead and other costs."

Paquet prepared its pay items for painting the bridges using an estimate received from a potential subcontractor. However, shortly before submitting its bid, Paquet received a substantially lower estimate from another subcontractor, O.J. Painting. Paquet contended that because it was "impractical" to revise the pay items corresponding to the bridge work, Paquet did not make any changes in its allocation with respect to the several painting items. Rather, Paquet lowered the prices of other pay items so that its overall bid, but not the painting pay items, reflected the O.J. Painting cost savings. The result was that Paquet submitted an unbalanced bid in which the pay items relating to the painting work included inflated amounts for cost, overhead and anticipated profit.

Paquet was awarded the contract, and NJDOT approved the subcontracts with the listed subcontractors, including O.J. Painting.

Shortly after Paquet was awarded the contract, the Occupational Safety and Health Administration revised its rules regarding the removal of lead-based paint. Paquet submitted claims for the additional anticipated costs caused by the OSHA change, which NJDOT rejected. Pursuant to contract specifications and because the parties could not agree on a revised price for the bridge painting work, NJDOT opted to delete the bridge painting work from Paquet's contract, issuing a deductive change and reducing the contract price accordingly.

Paquet brought suit for breach of contract and unjust enrichment, claiming that it was entitled to an equitable adjustment in the form of the difference between the original painting bid and the O.J. Painting bid. The trial court ruled in Paquet's favor but was reversed by the Appellate Division. Paquet petitioned for review to the New Jersey Supreme Court, which agreed to hear the case.


Ruling

The Supreme Court reviewed the contract provisions in question and, not finding applicable New Jersey law on the subject of equitable adjustments, reviewed federal law. Following this review, the Court ruled in favor of Paquet, awarding it an equitable adjustment equal to the difference between the original bridge painting bid and the O.J. Painting bid, minus any overhead and profit Paquet had built into the bridge painting bid items. However, the Court made clear that it was basing its ruling on several unique facts that the Court found were "unlikely to recur" in another case.

The first factor was the contract language at issue. The proscription against "unbalanced bids" was ambiguous under the circumstances. The Court noted that the "unbalanced bid" specification only prohibited "claims for additional compensation" and found that under one interpretation of this language, Paquet actually was not making a claim for additional compensation. Because Paquet was not seeking compensation over and above the original contract price, the Court reasoned, Paquet reasonably could have understood the language not to preclude the type of claim Paquet was making.

The second factor was that the painting work at issue was not scheduled to be performed until near the end of the project. The Court reasoned that Paquet's innocent explanation for the unbalanced bid was more believable than if Paquet had engaged in traditional front-end-loading to free up cash flow at the beginning of the project.

The third factor the court found significant was that NJDOT had approved the O.J. Painting subcontract, which contained the reduced bridge painting cost. The court reasoned that NJDOT was on notice of the unbalanced bid.

Finally, the Court found that NJDOT would be unjustly enriched if it were permitted to delete the entire cost of the bridge painting work, finding that "the plain fact is that Paquet performed hundreds of thousands of dollars worth of work for which it was not compensated."

The Paquet case teaches three important lessons. First, there is an inherent risk in the practice of front-end-loading a construction bid. While the Paquet court ultimately permitted equitable adjustment of the contract price to address problems arising from the unbalanced bid, the Court made clear it was only doing so because of the unique factors.

Second, because the specifications for competitively bid construction projects are provided by the owner, they generally will be construed liberally in favor of the contractor. This may mean that, as in the Paquet case, contract specifications that might at first blush appear to preclude a particular type of claim may contain an ambiguity which can be exploited in a contractor's claim for additional compensation.

Finally, the Paquet case reflects the general reluctance of the courts to allow a contract clause to confer a windfall benefit on an owner when a contractor makes an innocent mistake in its bid documents.


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.


Send This Report to a Colleague

Tools to Share, Organize, Comment on Information


©2002 ConstructionWebLinks, Inc.

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© ConstructionWebLinks, Inc.
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us