Construction Web guide: infrastructure, buildings, engineering, architecture
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us

Federal Preemption
Developer's Claim for Indemnity Against Architect for ADA and FHA Violations Rejected

Not Like Private Deals
City Contract May Not Be Modified Orally or by Course of Dealing, Court Holds

Business Risk Exclusion
CGL Insurer that Refused to Defend, Pay Claim Penalized, Held Liable

Little Known Hazard
Plumbers Burned as a Result of Natural Gas 'Odor Fade,' but Damage Award Reversed

Could Apply Broadly
Design Professional Denied Protection of Contract's Liability Limit by Florida Court

Part Of Lung Removed
Contractor Escapes Liability When Plaintiff Cannot Tie Infectious Fungus to Jobsite Dirt Stockpile

Disgorgement Order
Court Allows Discharge in Bankruptcy of Penalty for Violation of Contractor Licensing Law

Obligations Discharged
When Surety Takes Over Project, Owner Cannot Object to Replacement Contractor, Court Holds

Default Judgment
Notice, Accident, Own Work Defenses Rejected in Claims by General Contractor Against Plumber's Insurer

Previous Issues

Construction Industry News

Subcontractor Cannot Reasonably Be Expected to Provide Open-Ended Commitment of Work for a Fixed Sum


September 29, 2003


Back to Industry Newsletters
 

ConstructionWebLinks.com

Nebraska Beef Ltd. hired JB Contracting, Inc. to be its general contractor in renovating and adding to a slaughtering and beef processing plant. JB subcontracted with ABC Electric, Inc. for electrical work. ABC agreed to "furnish and install, complete all electrical work per plans and specs described on [the] drawings." The subcontract also provided that "[ABC] is aware that Nebraska Beef will add equipment requiring electrical services to its existing plant and new addition, not shown on plan or specified. [ABC] agrees to provide electrical service as required." JB agreed to pay ABC "($880,000) hereinafter called the 'Contract Price' plus all additions and less all deductions herein provided for.…"

Design of the project was incomplete at the time of bidding and subcontract execution. The drawings referred to in the contract covered only the proposed addition to the facility and not renovation of the existing project. Therefore, the critical, hotly disputed issue was whether the $880,000 contract price covered only the work described in the drawings or all electrical work needed to complete the entire project.

During construction, ABC billed for what it considered to be extra work, and Nebraska Beef refused to pay. Eventually, Nebraska Beef ordered ABC off the project.

ABC sued Nebraska Beef and JB in federal court and sought recovery in quantum meruit for work that it claimed was not covered by the contract. Nebraska Beef and JB counterclaimed, seeking expenses incurred in completing the electrical work.

ABC dismissed JB from the case. The District Court held there was no express or implied-in-fact contract between Nebraska Beef and ABC. It dismissed all breach-of-contract claims. The jury awarded ABC $335,190 on its quantum meruit claim and $356,280 on its promissory estoppel claim. Nebraska Beef's counterclaim was dismissed. It appealed.

The 8th U.S. Circuit of Appeals affirmed. ABC Electrical, Inc. v. Nebraska Beef, Ltd., 249 F.3d 762 (8th Cir. 2001). The appeals court held that a contract is not necessary to recover in quantum meruit. It held that under the Nebraska law of quantum meruit, ABC was entitled to recover the reasonable value of electrical services that it performed for Nebraska Beef's benefit in circumstances that would make it inequitable for Nebraska Beef not to pay. It noted that Nebraska Beef directly supervised the renovation, controlled the entire project, finally approved change orders and directly paid ABC for work performed.

The court also held that a party may not recover in quantum meruit for work it was obligated to perform under an express contract. But, a quantum meruit claim may supplement an express contract by seeking reasonable compensation for work not covered by the contract.

Thus, the key issue was what work ABC agreed to perform for $880,000. After hearing all of the evidence, the trial court ruled that the subcontract unambiguously limited the $880,000 price to the work described in the drawings and instructed the jury that ABC could recover in quantum meruit for construction work over and above that required by the drawings.

On appeal, Nebraska Beef argued that the subcontract unambiguously committed ABC to perform for $880,000 all electrical work for the entire project, excluding change orders and other extra work. Nebraska Beef thereby waived an argument that the subcontract was ambiguous, leaving only the issue of whether the contract was properly interpreted by the District Court. If Nebraska Beef had argued that the contract was ambiguous, it could have introduced extrinsic evidence of the parties' intent in contracting, and the factual dispute would have gone to the jury.

The appeals court found that looking only at the contract and without examining the parties' intent at the time of contracting, "JB would not reasonably have demanded, and ABC would not reasonably have made, an open-ended commitment to perform whatever work Nebraska Beef might decide in the future to require for a fixed price of $880,000." It noted that the renovation had not been designed at the time ABC contracted. The court found the language "Nebraska Beef will add equipment requiring electrical services" to be pertinent when read in conjunction with the contract provision that JB would pay ABC $880,000 "plus additions."


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.


Send This Report to a Colleague

Tools to Share, Organize, Comment on Information


©2003 ConstructionWebLinks, Inc.

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© ConstructionWebLinks, Inc.
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us