Construction Web guide: infrastructure, buildings, engineering, architecture
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us

Federal Preemption
Developer's Claim for Indemnity Against Architect for ADA and FHA Violations Rejected

Not Like Private Deals
City Contract May Not Be Modified Orally or by Course of Dealing, Court Holds

Business Risk Exclusion
CGL Insurer that Refused to Defend, Pay Claim Penalized, Held Liable

Little Known Hazard
Plumbers Burned as a Result of Natural Gas 'Odor Fade,' but Damage Award Reversed

Could Apply Broadly
Design Professional Denied Protection of Contract's Liability Limit by Florida Court

Part Of Lung Removed
Contractor Escapes Liability When Plaintiff Cannot Tie Infectious Fungus to Jobsite Dirt Stockpile

Disgorgement Order
Court Allows Discharge in Bankruptcy of Penalty for Violation of Contractor Licensing Law

Obligations Discharged
When Surety Takes Over Project, Owner Cannot Object to Replacement Contractor, Court Holds

Default Judgment
Notice, Accident, Own Work Defenses Rejected in Claims by General Contractor Against Plumber's Insurer

Previous Issues

Construction Industry News

Federal Contractor's Invoice for 99.99% of Contract Balance Is Not a Request for Final Payment; Release of Claims Not Required for Payment


September 16, 2002


Back to Industry Newsletters
 

ConstructionWebLinks.com

The Navy awarded a contract to U.S. General, Inc. (USG) for demolition of a timber pier and construction of a new pier supported by concrete piles at Point Loma Naval Station in San Diego. During construction, USG sought an equitable adjustment for several instances when concrete pile locations were changed. The Navy refused to grant the adjustments. USG submitted a differing site conditions claim, which the Navy's Contracting Officer denied. USG appealed to the Armed Services Board of Contract Appeals. ASBCA denied USG's differing site conditions claim but held that USG was entitled to an equitable adjustment under the contract's "Changes" clause for the net amount of $4,287. The Navy requested that USG submit an invoice and release of claims in order to receive payment for the award. USG refused in order to preserve its right to pursue other claims.

The contract incorporated standard Federal Acquisition Regulations clauses, including the "Payments Under Fixed-Price Construction Contract" clause (FAR 52.232-5, April 1989). The clause provides, in part, that the government shall pay the amount due the contractor after the contractor provides a release of all claims. (The contractor may except claims in stated amounts from the release.)

After contract completion, USG forwarded an invoice for the full amount remaining, $9,400. USG's appeal of its differing site condition claim still was pending. The Navy rejected USG's invoice because the final release of claims was missing. USG resubmitted the invoice but with a changed dollar amount. As explained in its cover letter, USG billed for 99.99 percent ($9,000) of the final amount, leaving $400 in the contract to "keep it open" until USG's claims were settled. The Navy did not pay this revised invoice. Five months later, USG again submitted a revised invoice for $9,000, leaving $400 to keep the contract open. Again, the Navy failed to pay. In a recorded telephone conversation, the Navy stated that it did not pay the invoice, even as revised, because USG refused to sign a release.

By letter, USG submitted a claim to the Navy to recover the $4,287 ASBCA award and the $9,000 revised invoice. The Contracting Officer's decision affirmed that the ASBCA award would not be paid without an invoice, but determined that the $9,000 revised invoice was proper and should have been paid. USG appealed the Contracting Officer's decision.

The ASBCA held that an invoice was not required for payment of a board award. It was not necessary for the Navy to lump the award with final payment, so no release was required before payment of the award.

ASBCA also held that the USG invoice for $9,000, revised to leave $400 to keep the contract open, was not a request for final payment and, accordingly, no release was required before payment of the invoice. The Navy should have paid the invoice as a progress invoice. In re U.S. General, Inc., ASBCA No. 52,041, 00-1 BCA 30,850 (ASBCA 2000).


If you would like to receive legal reports and updates by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.


Send This Report to a Colleague

Tools to Share, Organize, Comment on Information


©2002 ConstructionWebLinks, Inc.

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© ConstructionWebLinks, Inc.
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us