|
By Jesse B. Grove, III
To
an American lawyer specializing in construction law, the
idea that the contractor should have an equitable adjustment
of commercial terms to account for unforeseen and unforeseeable
subsurface conditions is axiomatic. To the extent that construction
law is taught in our law schools, the federal standard forms
are taken as the norm. Received wisdom, embodied in the
federal form since 1926, is that "Type I and Type II"
1/ changed conditions justify contractual relief.
Type
II changed conditions justify relief because it seemed to
our forebears that it is inherently unfair to burden a lump
sum contractor with the costs of overcoming obstacles that
no one, that is no reasonably experienced estimator, could
have foreseen. For those who are commercially driven, the
justification is that without such relief all bidders will
include contingencies for the unknown, thereby burdening
the employer with the obligation to pay for a risk that
may not (usually will not) ever materialize.
Type
I changed conditions have two additional justifications.
First, it is unseemly for the employer to benefit by publication
of (even unintentionally) misleading information, i.e.,
it smacks of fraud. Second, the fairness of the low bidder
scheme of procurement is compromised unless all bidders
can rely on the information given and thus occupy a level
playing field.
The
rest of world mostly agrees. 2/
The Hong Kong Exception
Hong
Kong does not agree and has not for the past decade or so.
Government's standard forms of contract for construction
place the risk of unforeseen and unforeseeable sub-surface
conditions on the contractor regardless of whether the contractor
was misled by insufficient or inaccurate information given
him by Government. Thus, the contractor must bear the financial
consequences (including liquidated damages for consequent
delay) of discovering the unexpected, whether it be natural
(e.g., faulting, fracturing, quicksand, vice rock,
rock vice soil, voids, material prone to settlement, peaks
and valleys in rock profile); toxic or hazardous (e.g.,
military ordnance, asbestos, hydrocarbons, PCBs, industrial
and human wastes); or manmade (e.g., utilities, pilings,
artifacts, antiquities, out-of-specification embedments
in reclamation areas).
The
author served as consultant to the Government of Hong Kong
Special Administrative Region in 1998 to make a "fundamental
review of the GCCs [General Conditions of Construction]
and in particular the allocation and management of risk
in the procurement of works projects... with recommendations
on any modifications necessary in the interests of public
finance based on international best practice." One
of the recommendations in the Final Report 3/ was
that Government should accept the risk of unforeseen and
unforeseeable physical conditions. The following justification
was offered:
12.5
The most important way to deal with this risk is to eliminate
it through pre-tender sub-surface and site explorations,
and designs that allow for suspected adverse conditions.
I understand from interviews that Government's designers
are up to the mark in this area. The fact remains that
there will always be some risk of unexpected adverse physical
conditions despite highly professional design efforts
having been applied. If the conditions should have been
appreciated but were not because of professional error
or if the design is unreasonably aggressive, the risk
will accrue to the designer (or design/builder).
12.6
The second most important mitigator is to make sure the
tendering contractors have adequate opportunity to make
a visual inspection of the site and consider all available
geological and exploratory information. This means that
Government should take the initiative to gather such information
and give it to the contractors with explicit warnings
of indicators of difficult conditions. Contractors may
be required to make their own interpretations, but that
is not a basis for withholding interpretations by Government's
experts. Since a well-drafted clause will prevent entitlement
to extra compensation in connection with conditions actually
foreseen, it is important to give the contractor every
opportunity to foresee.
12.7
It may occur that the contractor is misled by justifiable
reliance on insufficient or inaccurate information supplied
by Government. If this occurs by reason of professional
negligence, the risk will fall on the designer. In any
event, the risk should not fall on the contractor. The
first principle of risk allocation -- the Fault Standard
-- applies. It is unconscionable for Government to transfer
the risk of its own misrepresentation, and possibly not
enforceable at law. It should be noted that accepting
responsibility for representations made as to physical
conditions brings with it an alternative risk sharing
mechanism. Where Government wishes the contractor to bear
risk up to a certain level (e.g., one foot of soil settlement)
but is willing to accept the risk that conditions will
turn out to be worse, it can achieve this by representing
that conditions will be no worse than the specified level.
12.8
The risk that a truly unforeseeable and unforeseen physical
condition will be encountered remains to be considered.
Those who adhere to the Foreseeability Standard (which
includes the majority of international employers) have
no difficulty concluding that this risk should not be
transferred to the contractor. Those who prefer the Management
Standard argue that this risk belongs to the employer
because the employer has the best opportunity to control
and avoid the risk through pre-tender site exploration.
(It cannot seriously be argued that the contractor has
similar opportunity, and anyway employers do not want
multiple tenderers performing site explorations for a
whole host of practical reasons.) The Incentive Standard
can be argued either way, but it is noted that this is
an employer's risk under the ECC.
12.9
A compelling consideration is that this risk has potentially
catastrophic consequences beyond that which even a large
international contractor can bear. Thus a contractor who
has accepted the risk may have no alternative to an attempt
to pass it back to the employer through some stratagem
such as a strained theory of impossibility.
12.10
The risk is also impossible to quantify by estimate and
allow for in pricing. This means that contractors will
either throw a "guesstimate" contingency into
the tender price or take a gamble that all will be well.
The effect is that the winning tenderer will either be
the gambler or the low guesser. Frequently this will be
the thinly financed, low asset contractor who has little
to lose. It is not in Government's interest to attract
this calibre of contractor, nor to discourage highly competent,
conservative contractors.
12.11
On a practical level, contractors refuse to accept that
this risk should be borne by them. If forced to accept
the risk, they will strive mightily to offset the burden.
Excessive claimsmanship and adversarial conduct can be
expected. This creates the breeding ground for disputation
and its notorious consumption of resources.
12.12
Another reason for changing Clause 13 is that it is difficult
for the employer to administer, and it is probably being
administered inconsistently. When an unforeseen physical
condition -- say, an utility clash -- is encountered,
Government has two choices: leave the solution up to the
contractor or issue a variation order to overcome the
difficulty. The former leaves the financial burden on
the contractor, and the latter transfers it to Government.
Government's representative is thus motivated not to vary
the works even if that is (i) the most desirable or cheapest
solution or (ii) the best technical solution. This could
even lead to a viable contractor claim of impossibility
notwithstanding that a minor specification variation would
obviate the problem. 4/
The
foregoing convinced the Construction Industry Review Committee,
chaired by the Honourable Henry Tang, to recommend in its
January 2001 report that Government seriously consider adopting
the recommendation. 5/ So far, Government remains
unmoved.
Government
has not explained its position, but the countervailing considerations
are somewhat obvious. They are: (1) protection of the public
fisc, and (2) avoidance of disputes and litigation (or arbitration).
These are legitimate and important reasons.
Protection of the Fisc
Government
is entitled to insist on forward pricing of its contracts
in order to maintain appropriate control of its budget.
To the greatest extent possible, it is legitimate for Government
to avoid contracts that allow for surprising cost escalations.
The Central Artery Project in Boston, Massachusetts, has
come under serious political fire recently, not so much
because of the cost of the project as for the fact that
the potential cost was seriously under-appreciated until
near the end of construction. Many major projects in recent
memory might not have been commenced if the outturn cost
had been accurately predicted. Those with approval authority
resent the appearance of being gulled. Finally, the experience
in Hong Kong shows that Government can get away with transferring
changed conditions risk to the contractor. The contractors
may be howling, but they still are bidding.
It
is difficult to make the case that employer acceptance of
the risk of changed conditions actually will produce greater
value for money. This is the way it was argued in Grove
Report. 6/
23.1
To the extent that contractors are including contingencies
in their tender pricing for the risks in question, then
Government is paying for the risk whether it materializes
or not. Over many projects, this could be a substantial
waste of public funds as it will aggregate to a greater
amount than the direct costs of rarely occurring materialized
risk.
23.2
To the extent that contractors are not including contingencies,
the current risk allocations tend to encourage gambling
and guessing, which in turn leads to lower calibre contractors
receiving Government awards. These contractors will consume
more Government management resources and deliver lower
quality work less reliably than their more conservative
and competent competitors. They are more prone to financial
failure during performance and more likely to embroil
Government in disputes. Over many projects, this too could
be a net waste of public funds.
23.3
Even the most reputable and competent contractors will
do their utmost to transfer risk back to the employer
or recoup losses by other means if the risk allocation
is viewed by them as inappropriate, unfair by international
standards or threatening to company survival. This means
disputes. And the disputes likely will be hard to resolve
because they will be thin on legal and contractual justification
and long on desperation. The cost to Government of dispute-ridden
projects is enormous. The direct costs of defending alone
are very high. The indirect costs of losing focus on and
control of the construction process can be much greater.
In my opinion, these costs will be higher than the direct
costs of accepting the risks which I have identified as
candidates.
23.4
I cannot prove the cost equation by empirical evidence,
and I do not believe that others can. Moreover, I do not
fully trust surveys of contractors, even though the contractors
have the best information. But, I can say that many who
have studied these issues agree with my conclusions.
23.4.1
To begin with, every Government, every international employer
and every financing party (such as the World Bank) that
has adopted GCCs with risk allocations congruent with
those I recommend has done so not out of altruism but
because of a conclusion that there is financial justification.
23.4.2
The sponsors of the international forms of contract identified
in paragraph 3.5 (ICE, FIDIC, etc.) can be taken to agree.
23.4.3
The Mass Transit Railway Corporation can be taken to agree.
23.4.4
The Construction Industry Institute, the Center for Public
Resources, the American Society of Civil Engineers, and
the Risk Allocation Subcommittee of a Joint Working Party
of the Australia National Public Works Conference and
the National Building and Construction Council all agree.
23.4.5
A plethora of respected industry savants have expressed
agreement in their published works.
23.5
To the contrary, however, many employers take the view
that their interests are best served by transferring as
much risk to the contractor as the market will bear. I
suggest that there usually are special reasons for this
which do not apply to Government public works. Certainly
the rationalia are different for the one time or occasional
employer than for a repeat employer on the scale of the
Government of the Hong Kong SAR.
One
can hardly blame the protectors of the public fisc for focusing
on the admission in the first sentence of paragraph 23.4.
Avoidance of Disputes
Critics
of changed conditions entitlement point out that the usual
contract clauses are difficult to administer because they
embody a subjective standard. The test of entitlement is
foreseeability, i.e., that which is foreseeable by an experienced
bidder does not qualify whereas that which is not, and which
was not actually foreseen, does. This puts contract entitlement
into the murky realm of tort law. It invites the engagement
of experts who can be expected to have opinions favoring
the party writing the paycheck. The end result is an unwelcome
lack of predictability. Only a judge, jury or arbitrator
can say for sure. Thus, most cases will wind up consuming
the large resources necessary to obtain third-party dispute
resolution.
There
is merit to this argument but not as much as might appear
facially. Again, having to admit lack of empirical evidence,
it could be said that most changed conditions situations
present circumstances that are easy to evaluate against
a foreseeability standard. One should expect to encounter
sand in the Middle East but not perched water. In fact,
most changed conditions situations that involve the presence
of a wholly different material than expected are easy to
evaluate. The rub comes when the risk of what was encountered
was known generically but not to the degree of occurrence.
The
Channel Tunnel (if one glosses the facts to suit) illustrates
the problem. Everyone knew what the tunneling medium (chalk
marl) would be and the suitability of that material for
using tunnel boring machines (TBMs). Everyone knew, as well,
that some water infiltration would occur because the marl
is somewhat fractured and fissured, especially near the
shore, although otherwise quite impervious. What no one
knew for sure is just how much water infiltration over what
length of tunnel might occur. This was extremely important
because there are two kinds of TBMs: those that can stand
water infiltration and those that cannot. The former are
expensive to build and slow and expensive to operate; not
ideal for what everyone knew most of the Chunnel length
would be like. The latter are cheaper to build and can run
like a greyhound, but could get stuck in a bad area with
disastrous cost consequences.
The
French chose the tortoise; the British chose the hare. The
French encountered conditions that were a little more favorable
than a pessimistic bidder would have expected, and the British
hit ground that was a little worse than either an optimistic
or a middle view would have predicted. The French proceeded
ponderously without incident, and of course the British
hare got stuck, had to be rebuilt and, only after huge cost
consequences, got through the bad ground and then set records
for daily progress.
The
British wanted changed conditions relief. The employer took
the view that conditions were not changed (or unforeseen,
much less unforeseeable), just a little worse than the contractor
consciously gambled. The British pointed out that the employer
would have paid, and did pay the French, for being conservative.
Moreover, the British machine eventually performed so well
that it shot right by "Point M" (the planned meeting
point) while the French machine still was plodding ahead.
In the circumstances, the employer could be said to be not
disadvantaged by a somewhat daring British decision.
It
is hard to say how many tough cases like the Channel Tunnel
arise each year, but experience suggests that it is not
a few. This raises the question whether some better formulation
of the changed conditions clauses could be found.
A Better Way Forward
The
possibility of encountering unexpected subsurface conditions
now is frequently treated as a risk that should be allocated
on a case-by-case basis. While a Government cannot negotiate
purpose-built clauses in all of its hundreds of procurements
a year, private parties frequently do, and Governments can
to some extent. Certainly Governments can custom craft the
allocation of subsurface risk for huge infrastructure projects.
In fact, that is exactly what happened with the Hong Kong
Airport project.
There
are any number of ways to carve the risk. It can be done
by quantity, as when the contractor takes the risk of ground
settlement up to a point (say 3 feet) and the employer beyond
that point. In the Chunnel case, it could have been done
by establishing a break point in terms of cubic feet per
second. In a pipeline project, the contractor could be directed
to assume a certain footage of rock ditch in its bid, and
the employer would then pay an unit price extra for exceedance.
No
matter how it is done, project-specific risk allocation
brings with it the opportunity for shared risk. "Dead
bands," "bogeys" and less-than-adequate unit
prices are the most common devices. The idea is to keep
the contractor incentivized to manage and overcome the risk
while relieving it of disastrous cost exposure.
It
should not be forgotten that specific risk allocation still
leaves open the question of who takes the default position
if something happens that was not mentioned at all. To illustrate,
consider that the typical pipeline contract provides for
unit price protection if the contractor hits rock, high
water tables or obstacles that prevent normal sequencing
of the work. Every other kind of subsurface risk is left
to the contractor, and that has proven to be commercially
acceptable. By comparison, generic changed conditions clauses
require the employer to assume the default position. This
may be commercially unnecessary.
Conclusion
Changed
conditions clauses are here to stay and are desirable for
fairness, commercial benefits to both parties and congruency
with public bidding. They mostly work well, but the subjective
standard employed can lead to disputation. An improvement
that is obvious for a major project is to use a project-specific
risk allocation scheme that will provide necessary protection
even though the default position may remain with the contractor.
If you would like to receive legal reports and updates
more quickly, by e-mail, click
here and fill out the mailing list form.
For more information about the issues covered in this report, please contact Paul Berning in our San Francisco office at 415-369-7229 or at pwberning@thelen.com or contact your Thelen attorney. For more information about Thelen's Construction and Government Contracts Department, click here.
ENDNOTES
1/
Type I = different than represented; Type II = unforeseeable.
2/
Appended to this paper is a survey of changed conditions
clauses in well-known forms of contract.
3/
Known today as the "Grove Report" and available
at:
www.constructionweblinks.com/Resources/
Industry_Reports_Newsletters/Nov_6_2000/grove_report.htm
4/
"Grove Report," supra at:
www.constructionweblinks.com/Resources/
Industry_Reports_Newsletters/Nov_6_2000/grove_report.htm
5/
"Tang Report," January 2001, p. 74
6/
"Grove Report," supra at: www.constructionweblinks.com/Resources/
Industry_Reports_Newsletters/Nov_6_2000/grove_report.htm
APPENDIX
A.
Contract Forms Referenced:
1.
Fédération Internationale des Ingénieurs-Conseils
(International Federation of Consulting Engineers, or FIDIC),
Conditions of Contract for Works of Civil Engineering
Construction, Part I, General Conditions, Fourth Edition
(1987, reprinted in 1988 and 1992 with amendments) ("FIDIC").
2.
Australian Standard, AS 4000 - 1997, General Conditions
of Contract (1997) ("Australian Standard").
3.
The Institution of Civil Engineers (United Kingdom), The
Engineering and Construction Contract, Second Edition
(1995, reprinted with corrections May, 1998)
("ECC").
4.
Federal Acquisition Regulation (United States), Title 48,
Subpart 52.2, Code of Federal Regulations, Text of Provisions
and Clauses (1997) ("FAR").
5.
American Institute of Architects (United States), AIA Document
A201-1997, General Conditions of Contract for Construction
(1997) ("AIA").
6.
Engineering Advancement Association of Japan (Japan), ENAA
Model Form International Contract for Power Plant Construction
(Turnkey Lumpsum Basis), Vol. I, General Conditions (1996)
("ENAA").
7.
Construction Industry Development Board (Singapore), Public
Sector Standard Conditions of Contract for Construction
Works (1995) ("Singapore").
8.
GC/Works/1 Without Quantities, Contract for Building
and Civil Engineering Major Works, General Conditions
(1998) ("GC/Works/1").
9.
The Institution of Civil Engineers (United Kingdom), The
New Engineering Contract, First Edition (1993) ("EC
1993").
10.
The World Bank, Standard Bidding Documents, Procurement
of Works (1995) ("World Bank").
11.
Joint Contracts Tribunal for the Standard Form of Building
Contract, Standard Form of Building Contract, Private
With Quantities (1980 Edition, incorporating amendments
issued through April 1998) ("JCT 80").
12.
Joint Contracts Tribunal for the Standard Form of Building
Contract, Standard Form of Building Contract With Contractor's
Design (1981 Edition, incorporating amendments issued
through April 1998) ("JCT 81"),
13.
Institution of Civil Engineers, Association of Consulting
Engineers and Federation of Civil Engineering Contractors,
ICE Conditions of Contract, (Sixth Edition, January
1991; reprinted with amendments, November 1995; reprinted
November 1997) ("ICE 6th Edition").
B. Ground Conditions Provisions
FIDIC,
World Bank: Contractor entitled to additional costs
for expenses and time extension for delays resulting from
physical obstructions or conditions, except climatic conditions,
not reasonably foreseeable by an experienced contractor
(Sub-Clause 12.2) or resulting from fossils, coins, articles
of value or antiquity and structures and other remains or
things of geological or archaeological interest discovered
at site (Sub-Clause 27.1).
Australian
Standard: Contractor entitled to additional costs incurred
upon encountering minerals, fossils or relics (Subclause
24.3). Contractor entitled to variation pricing (set by
agreement, in contract or as otherwise reasonable, including
amount for overhead and profit) for costs resulting from
latent physical conditions on or near site, including artificial
things but excluding weather conditions, that differ materially
from physical conditions which reasonably should have been
anticipated by competent contractor after reviewing tender
information (Subclauses 25.1 to 25.3, 36.4). Time extension
also is provided as a form of relief for delays resulting
from such conditions (Subclause 34.3).
ECC,
EC 1993: Contractor entitled to adjustment of contract
price and/or schedule for costs/delays resulting from physical
conditions within site, other than weather conditions, that
an experienced contractor would have judged at time of contracting
to have such a small chance of occurring that it would have
been unreasonable for it to have allowed for them (Clause
60.1.12).
FAR:
Contractor entitled to equitable adjustment of contract
price and/or time for costs/delays resulting from sub-surface
or latent physical conditions at site differing materially
from those indicated in contract or unknown physical conditions
at site that are of unusual nature and differ materially
from those ordinarily encountered and generally recognized
as inhering in work of character provided for in contract
(Section 52.236-2).
AIA:
Contractor entitled to equitable adjustment of contract
price and/or time for costs/delays resulting from sub-surface
or otherwise concealed physical conditions that differ materially
from those indicated in contract documents or unknown physical
conditions of unusual nature that differ materially from
those ordinarily found to exist and generally recognized
as inherent in similar construction activities (Subparagraphs
4.3.4, 8.3.1; Paragraph 10.3).
ENAA:
Contractor entitled to additional costs for expenses
and time extension for delays resulting from physical conditions,
other than climatic conditions, or artificial obstructions
on site not reasonably foreseeable by experienced contractor
on basis of information provided by owner and information
obtainable through visual site inspection (GC 35.1 to 35.3).
Singapore:
Contractor entitled to additional costs for expenses
and time extension for delays resulting from artificial
obstructions that are encountered while carrying out sub-surface
works and are not reasonably foreseeable by experienced
contractor (Clauses 5.2; 22.1 (g)).
GC/Works/1:
Contractor entitled to adjustment of contract sum for value
of work carried out or omitted and/or extension of time
for delays due to ground conditions (excluding those caused
by weather but including artificial obstructions) that he
did not know of and that he could not reasonably have foreseen
having regard to any information that he had or ought reasonably
to have ascertained. (Conditions 7 (2) to (5); Condition
36 (2) (d)). Contractor entitled to variation pricing for
actions taken upon discovery of fossils, antiquities or
objects of interest or value (Condition 40 (2) (n)).
JCT
80 and 81: These are remeasurement forms that effectively
place much of the ground condition risk on the employer.
The only express provision requires that the amount of Contractor's
direct loss and/or expense resulting from discovery and
specified treatment of fossils, antiquities and other objects
of interest or value at site shall be added to Contract
Sum, and time may extended for delays resulting from Architect's
variation instructions with respect to such items (Clause
34.3).
ICE
6th Edition: Contractor entitled to additional costs
plus reasonable profit and an extension of time for delays
resulting from physical conditions (other than weather conditions
or conditions due to weather conditions) or artificial obstructions,
which conditions or obstructions could not reasonably have
been foreseen by an experienced contractor (Clauses 12 (1),
12 (6)). Even if Engineer believes such conditions were
reasonably foreseeable, any resulting variation ordered
by Engineer shall be valued according to specified rates
or prices or approximations thereof and included in contract
price (Clause 12 (5)).
©2001 Thelen Reid Brown Raysman & Steiner LLP
|