|
By Andrew D. Ness
Risk
management for the construction of capital-intensive projects
should begin at the very earliest stages of project planning
and continue through project completion. Straightforward
risk-management techniques are available to an owner of
a construction project at the project planning, contract
formation and contract administration phases of the project.
If followed, these techniques will both reduce the chance
of major claims on the construction project and will put
the owner in a position to successfully defend against any
claims that may arise.
Claims Avoidance Techniques
Contract
Documents. During the design phase of a construction
project, an owner's ideas, concepts and project requirements
are transformed into detailed plans and specifications that
will be used by the contractor to construct the project.
It is important that an owner, in conjunction with the architect/engineer,
exercise the utmost care and consideration when making decisions
early in the design phase to minimize the impact of any
disputes on project progress.
Proper
planning and careful review of project plans and specifications
can substantially minimize the likelihood of disputes and
provide a basis for timely resolution of any problem that
may occur.
It
may be advisable for the owner to establish an independent
contract document review team that will review the project
documents as a whole. The contract review team should look
for ambiguities, inconsistencies and conflicts in the project
documents. Persons not involved in the preparation of the
original documents may provide a fresh look and be better
able to identify deficiencies in the documents than the
people who prepared them.
Schedule.
The project schedule is one of the most important considerations
in construction project management. Schedule control is
critical if the owner, contractor and all other parties
to the contract expect to complete the project on time,
within budget and in accordance with the plans and specifications.
A
good scheduling specification should include a combination
of provisions addressing all elements in the development,
review, approval and monitoring of a schedule. For example,
an owner should consider including a schedule in the bid
documents that sets forth the major project milestones.
This will enable the contractor to more realistically evaluate
the time and phasing requirements of the project and to
more accurately assess the lead time needed for the procurement
of materials and equipment, to estimate the project staffing
and labor requirements, and to anticipate the general weather
conditions for different phases of the project.
Typically,
an owner requires that the contractor prepare and submit
a construction schedule in accordance with the owner's needs,
as provided in the owner's scheduling specification. The
contractor should be required to assign a duration to each
activity shown on its schedule and to provide an estimate
of the time required to complete the activity. Further,
the specification should state how frequently the approved
project schedule must be updated and should describe how
monthly progress payments will be calculated. By providing
a strong scheduling specification in the early phases of
the project, the owner can ensure that the contractor's
schedule accurately reflects the project status, thereby
ensuring that the project schedule is a useful management
tool.
Change
Orders. From the owner's perspective, managing a dispute-free
project also requires, to the extent possible, that all
change orders are prepared, evaluated and executed in a
timely fashion. When a situation warranting a change order
arises, the owner and the architect/engineer should move
quickly to document all facts surrounding the need for the
change. The direct costs of performing the changed work
and the potential impact the change may have on the project
schedule should be promptly analyzed. Ideally, the construction
contract should require that a change order be made by written
order of an authorized officer of the owner and designated
specifically as a change order.
In
the typical construction contract, the contractor is required
to submit a written notice of claim within a certain number
of days after receipt of an owner directive if the contractor
wishes to obtain an equitable adjustment for the directive.
Failure to do so constitutes a waiver of the contractor's
claim rights under most circumstances if the owner can show
prejudice as a result of the delayed claim.
Construction
projects rarely are completed without encountering some
problem not anticipated by the owner or the contractor,
such as errors in the construction plans, site conditions
differing from what was expected, new or improved construction
methods becoming available, or changing owner requirements.
Accordingly, a contract clause that allows the owner to
modify the contract in response to changing circumstances
during the performance of the contract is critical. Such
a clause provides the owner with the flexibility to meet
unforeseen contingencies without being required to negotiate
an entirely new contract.
The
owner could encounter schedule delays if the contract does
not explicitly provide for the performance of a change order
pending final agreement on its pricing. To avoid this problem,
the owner should include a contract provision requiring
the contractor to proceed with the work pending determination
of any contract price or schedule adjustment.
Responding to Contractor Claims
When
an owner is made aware of or receives notice of a potential
claim by a contractor, the owner immediately should make
an initial review of all of the circumstances and related
events involving the potential claim. Often, a contractor's
problem can be resolved quickly by objectively evaluating
the contractor's concern and applying "the rule of
reason" before the problem escalates into a full-blown
dispute. In this way, early evaluation of the facts involving
the potential claim can focus the issues and increase the
likelihood of a prompt, good faith, negotiated settlement.
Proper
Submission of Claims. At the outset, the owner should
determine whether the contractor's claim has been submitted
completely, correctly and in accordance with the contract
requirements. For example, the owner should determine whether
the contractor has provided timely notification of the claim
under the terms of the contract. The owner should ensure
that the contractor has submitted the necessary supporting
factual information, cost and schedule data, and project
documentation to back up any claim asserted.
The
speed with which a claim can be analyzed is dependent, in
part, on how well it is organized. Accordingly, the owner
should require that the contractor submit the claim, with
supporting documentation, in a form that sets forth and
identifies the primary, secondary, and any indirect claim
in a clear, concise manner. The owner also should require
the contractor to identify the applicable contract provisions
and the cost and schedule impacts related to each issue.
A claim that is not properly supported should be returned
to the contractor for resubmission.
Factual
Investigation. The owner usually should conduct an immediate
independent investigation of a contractor's claim. Often
this is best accomplished with the assistance of legal counsel,
depending upon the amount of the claim and the complexity
of the project. The documentation and presentation of the
facts in defense of the claim can have a significant impact
on the outcome of construction litigation and should be
carefully considered. The following steps may be taken during
a preliminary investigation of a claim to assist in its
efficient resolution:
1.
The project design professional should be put on notice
of potential liability if the claim involves a construction
failure and the designer's work potentially contributed
to the failure.
2.
A thorough site investigation should be conducted
to determine the facts surrounding the claim and to record
in detail relevant observations of the site. Often, it is
advisable to make a photographic or video survey of the
site to keep a record of any construction failure or construction
delay.
3.
All of the relevant project correspondence should
be collected and organized.
4.
The people who are most knowledgeable about the facts
relating to the claim should be interviewed.
5.
If the owner prepares a report of the investigation,
it should include only facts and summaries of interviews.
The report should not include speculation about possible
causes of the failure or draw any final conclusions about
the facts. One reason to avoid including speculation and
conclusions in an investigation report is that if the claim
becomes the subject of litigation, the owner likely will
be required to turn over the report to the contractor as
part of the discovery process. It is more appropriate to
have conclusions drawn by a subject matter expert who is
qualified to offer an opinion based on the facts as set
forth in the investigation.
Legal
Analysis. After the factual investigation of a claim
has been completed, legal counsel should conduct an analysis
of the strengths and weaknesses of the owner's legal position.
The first step is to determine whether the contractor has
met its burden of proof of entitlement. If the contractor
establishes entitlement to a claim, then the contractor
must prove that it incurred damages arising from the claim.
Possible Defenses
If
an owner is presented with a timely and well-supported claim
by a contractor, a number of legal defenses may be applicable,
including:
Notice
Requirements. Often, a construction contract will contain
a written notice provision governing claims for extra work,
excusable delay or differing site conditions. If a contractor
fails to give proper written notice of a claim, an owner
may assert this failure as a defense to the contractor's
claim.
Exculpatory
Clauses. An exculpatory clause such as a "no damages
for delay" clause may be used by an owner to defend
against a delay claim brought by a contractor. Enforcement
of such exculpatory clauses varies depending on the jurisdiction,
but the no damage for delay clause generally is held to
be valid and not contrary to public policy.
Prior
Settlement Release and Waiver. A change order issued
by an owner and executed by a contractor may result in a
waiver of a future claim by the contractor for the same
event. Thus, the owner should review any prior change orders
that relate to a contractor's claim.
Excusable/Noncompensable
Delay. If an owner has not assumed the risk of a certain
event, the owner ordinarily is not liable for extra costs
incurred by the contractor as a result of such event. As
a result, a contractor may be entitled to a time extension
but not be entitled to additional compensation from the
owner for extra costs resulting from the event for which
the owner did not assume the risk. For example, a contractor
may be entitled to a schedule extension for delays caused
by excessive adverse weather conditions but may not be entitled
to recover additional costs arising from the delays if the
owner did not assume the risk of adverse weather.
Breach
of Contract. If a contractor is bringing a claim against
the owner on a contract that has not been substantially
or properly performed by the contractor, the owner may,
in certain circumstances, be able to defend against a contractor's
action by asserting that the contractor is in breach of
the contract.
Abandonment.
A contractor that abandons its performance obligations under
a contract may be in breach of contract. Whether such abandonment
will constitute an absolute defense to a contractor's recovery
for work already performed will depend on many factors,
including whether the contract can be divided into discrete
segments. If a contract is divisible, then an owner may
be less able to assert abandonment as an absolute defense
to a contractor's claim for recovery based on work already
performed on the contract.
Statutes
of Limitation. The statute of limitations for contract
actions varies by jurisdiction. It is possible that if a
contractor asserts a claim against the owner based on facts
occurring far enough in the past, an owner may have a defense
against the claim based on the applicable statute of limitations.
Liability
of Other Parties. On occasion, a claim against an owner
may arise through no fault of the owner. In some instances,
when the fault lies with a third party acting as an agent
or representative of the owner, the owner may be liable
on the claim. However, in other situations, the owner's
contractual relationship with the third party may be such
that the owner is relieved of liability for the errors of
the third party or for a contractor's mistaken reliance
on the authority of the third party.
Mitigation.
The contractor has an obligation to mitigate any damage
that results from a problem on a construction project. Accordingly,
an owner may be able to defend against a claim in part by
introducing evidence that the contractor should have taken
steps to mitigate the problem and to thereby reduce the
amount of damage incurred.
Fraud
and Misrepresentation. In extreme cases, when an owner
is presented with a claim for extra work that the owner
believes to be false or grossly misrepresented, an owner
may have an action against the contractor for fraud.
Conclusion
Proper
project planning and contract preparation in the initial
stages of a project can go a long way toward minimizing
the impact of disputes on a construction project. Effective
contract drafting, project document review and contract
administration are important to the long-term success of
a construction project. In particular, provisions dealing
with project milestones and schedule, changes and notice
provisions all are important to effective management of
the claims process. Favorable resolution of a construction
dispute depends on a swift and effective response by the
owner to the contractor's specific concerns. An owner's
response should include a review of the contractor's claim
to ensure that it complies with the contract requirements,
a preliminary investigation of the facts, a review of the
applicable contract provisions and an analysis of the applicable
law and available defenses. In this way, an owner will be
in the best position to respond quickly and appropriately
to a contractor's claim and to ensure that the claim will
have the least impact on the success of the project.
If you would like to receive legal reports and updates
more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.
©2000 ConstructionWebLinks, Inc.
|