Construction Web guide: infrastructure, buildings, engineering, architecture
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us

Federal Preemption
Developer's Claim for Indemnity Against Architect for ADA and FHA Violations Rejected

Not Like Private Deals
City Contract May Not Be Modified Orally or by Course of Dealing, Court Holds

Business Risk Exclusion
CGL Insurer that Refused to Defend, Pay Claim Penalized, Held Liable

Little Known Hazard
Plumbers Burned as a Result of Natural Gas 'Odor Fade,' but Damage Award Reversed

Could Apply Broadly
Design Professional Denied Protection of Contract's Liability Limit by Florida Court

Part Of Lung Removed
Contractor Escapes Liability When Plaintiff Cannot Tie Infectious Fungus to Jobsite Dirt Stockpile

Disgorgement Order
Court Allows Discharge in Bankruptcy of Penalty for Violation of Contractor Licensing Law

Obligations Discharged
When Surety Takes Over Project, Owner Cannot Object to Replacement Contractor, Court Holds

Default Judgment
Notice, Accident, Own Work Defenses Rejected in Claims by General Contractor Against Plumber's Insurer

Previous Issues

Construction Industry News

Contractor's Claim Barred by Failure to Give Notice


June 19, 2000


Back to Industry Newsletters
 

(A revised version of this article appears in The Construction Lawyer, Volume 20, No. 3, July 2000, published by the American Bar Association's Forum on the Construction Industry.)


By John W. Ralls

A North Dakota-based earth-moving contractor encountered many more rocks than it expected in performing work for the State of Wyoming. Although the contractor initially anticipated having to move 600 cubic yards of rock, it uncovered approximately 120,000 cubic yards of rock. The contractor began encountering excessive rock in January 1991 but did not request additional compensation based on unforeseen site conditions until May 28, 1991.

The contract contained two notice clauses. The first, entitled "Unforeseen Physical Conditions," provided: "CONTRACTOR shall promptly notify OWNER and ENGINEER in writing, within fifteen days, of any subsurface or latent physical conditions at the site differing materially from those indicated on the Surface or in the Contract Documents."

The second notice clause, entitled "Change of Contract Price," provided: "Any claim for an increase in the Contract Price shall be based on written notice delivered to OWNER and ENGINEER within fifteen days of the occurrence of the event giving rise to the claim."

The State of Wyoming denied the claim, and the contractor sued the state. The contractor was represented in the suit by a North Dakota lawyer, who associated Wyoming counsel. The state moved for summary judgment on grounds that the contractor failed to follow the contractual notice requirements and that the contractor's claim was insufficient pursuant to the Wyoming Governmental Claims Act. The Wyoming trial court granted the state's motion.

The contractor failed to appeal the summary judgment ruling, apparently because its North Dakota attorney was unfamiliar with the Wyoming deadline for appeal from a summary judgment order. The contractor then sued its North Dakota attorney in North Dakota state court for malpractice. The attorney in the malpractice action filed a motion for summary judgment on the ground that the summary judgment ruling was proper under Wyoming law.

The contractor contended that the North Dakota attorney not only failed to file a timely appeal but also failed to argue that the "Unforeseen Physical Conditions" clause applied, not the "Change of Contract Price" clause. The contractor contended "which contract provision applies is significant because while determining 'the occurrence of the event giving rise to the claim' requires application of an objective test, determining [the existence of] 'any subsurface or latent physical conditions at the site differing materially from those indicated on the Surface or in the Contract Documents' requires application of a subjective test.…"

The court rejected this argument on the ground that the "Unforeseen Physical Conditions" clause "must be interpreted from the perspective of what the contractor knew, or what a reasonable contractor should have known, under the circumstances." The court concluded that the contractor knew or reasonably should have known more than 15 days before May 28, 1991, both that an event triggering a claim for a contract price increase and a subsurface condition differing materially from the surface conditions existed. Dan Nelson Constr., Inc. v. Nodland & Dickson, 2000 N.D. 61, 2000 N.D. LEXIS 63 (2000).

The court also rejected the contractor's arguments that the state had waived, or should be estopped from asserting, the notice requirements. "Even if the State had actual knowledge of [the contractor's] claim, actual knowledge of a potential claim by the government does not in itself estop the government from raising the untimely filing of the claim as a defense absent a showing 'that the delay in filing was induced by [the government], or that [the government] misled [the claimant] as to the need to file a claim,' " quoting Cranston v. Weston County Weed & Pest Board, 826 P.2d 251, 256-57 (Wyo. 1992).

The court also found that the general contractor's claim was not a sufficiently "itemized statement in writing" for purposes of the Wyoming Governmental Claims Act. Although the claim described the locations of the rocks and the additional amounts expended to remove the rocks in each location, the claim was insufficient "[g]iven the Wyoming Supreme Court's strict construction of the claims procedure statute" in prior cases, citing In re Board of Trustees of the University of Wyoming v. Bell, 662 P.2d 410 (Wyo. 1983) and Amrein v. Wyoming Livestock Bd., 851 P.2d 769 (Wyo. 1993).


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.


Send This Report to a Colleague

Tools to Share, Organize, Comment on Information


©2000 ConstructionWebLinks, Inc.

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© ConstructionWebLinks, Inc.
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us