|
ConstructionWebLinks.com
Parties to construction contracts usually reduce to writing
their original agreement for the work contemplated. It is
not uncommon for the parties to alter or modify their contract
during construction. Sometimes those modifications or changes
are not put into writing. The highest courts of two states
recently examined whether a contractor can recover for extra
work without a written change order and came to different
conclusions, in large part based on contract provisions.
In
CMC Enterprises, Inc. v. Ken Lowe Management Co.,
525 S.E.2d 295 (W.Va. 1999), the West Virginia Supreme Court
ruled that a contractor could recover for the additional
work that it performed under an oral modification of the
original contract. The case arose after a property owner
hired a contractor to remodel a Social Security Administration
building under a lump sum contract. The original contract,
which the contractor drafted, required that the contractor
perform all work in accordance with the building specifications
set out in related contract documentation. The contract
was silent as to whether change orders or modifications
had to be in writing.
On
the day when the contractor began work on the building,
the Social Security Administration wrote to the property
owner, cautioning the owner against following the floor
plans outlined in the original contract documentation. A
little over a week later, the contractor received the new
floor plans with new specifications. The property owner
informed the contractor on two separate occasions to follow
the specifications in the new floor plans, which the contractor
did. Less than two months after it began working on the
project, the contractor completed the remodeling work. The
property owner then refused to pay the contractor's invoice
for the additional work required under the modifications
to the original contract.
The
contractor sued the owner for breach of contract, alleging
that it was entitled to the value of the additional work
it performed on the project arising from the modifications
to the plans. The trial court found in favor of the contractor,
holding that to find otherwise would permit the owner to
become unjustly enriched.
The
West Virginia Supreme Court affirmed the trial court. The
Supreme Court found that the parties orally modified the
contract to include additional work not contemplated under
the original contract and that the original contract did
not dictate whether or not such changes had to be in writing.
The contractor was entitled to recover its costs for the
additional work it performed, and the owner was not entitled
to benefit from the contractor's services without paying
the contractor.
In
contrast, the Maryland Court of Appeals reached a different
conclusion in County Commissioners of Caroline
County v. Roland Dashiell & Sons, Inc., 358 Md.
83, 747 A.2d 600 (2000). In that case, the county and the
contractor entered into a lump sum contract involving a
county jail. The contract included the AIA A201 General
Conditions. A201 requires that claims under the contract,
including to adjust the contract terms, for additional costs
and for time, be submitted in writing. Although the contractor
sought a change order increasing the price of the contract
and extending the completion date, it failed to submit its
requests in a timely fashion under the terms of the contract.
The
contractor filed suit against the county, seeking damages
for the extra cost of work and delays and relief from liquidated
damages. The trial court granted the county's motion for
summary judgment, which the contractor appealed. The Court
of Special Appeals affirmed the trial court in part. However,
it disagreed with the trial court as to whether the contractor
was entitled to recover on its quantum meruit or unjust
enrichment claim against the county. The county brought
a writ seeking review by the Maryland Court of Appeals.
The
Maryland Court of Appeals held that the express, written
agreement between the contractor and the county barred the
contractor's claim for unjust enrichment. The court noted
that the contractor entered into an express contract with
the county, and the contract, via A201, contained provisions
relating to the contractor's recovery of money for extra
work at the jail. An express contract existed between the
contractor and the county, which defined the rights and
remedies available to the contractor under the terms of
the contract. To permit the contractor to recover for its
work in this situation, the court reasoned, would permit
the contractor unilaterally to amend the contract and escape
the terms of the original contract. There was no unjust
enrichment because the county was entitled to have the contract
strictly followed.
The
West Virginia contract contained no such requirement, which
proved to be of benefit to the contractor and a significant
factor to the court. Both cases illustrate the extreme risk
taken by contractors that perform extra work without written
change orders.
If you would like to receive legal reports and updates
more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.
©2000 ConstructionWebLinks, Inc.
|