Construction Web guide: infrastructure, buildings, engineering, architecture
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us

Federal Preemption
Developer's Claim for Indemnity Against Architect for ADA and FHA Violations Rejected

Not Like Private Deals
City Contract May Not Be Modified Orally or by Course of Dealing, Court Holds

Business Risk Exclusion
CGL Insurer that Refused to Defend, Pay Claim Penalized, Held Liable

Little Known Hazard
Plumbers Burned as a Result of Natural Gas 'Odor Fade,' but Damage Award Reversed

Could Apply Broadly
Design Professional Denied Protection of Contract's Liability Limit by Florida Court

Part Of Lung Removed
Contractor Escapes Liability When Plaintiff Cannot Tie Infectious Fungus to Jobsite Dirt Stockpile

Disgorgement Order
Court Allows Discharge in Bankruptcy of Penalty for Violation of Contractor Licensing Law

Obligations Discharged
When Surety Takes Over Project, Owner Cannot Object to Replacement Contractor, Court Holds

Default Judgment
Notice, Accident, Own Work Defenses Rejected in Claims by General Contractor Against Plumber's Insurer

Previous Issues

Construction Industry News

Problems in Enforcing Subcontractor Bids Are Illustrated by Four Recent Cases


February 24, 2003


Back to Industry Newsletters
 

By Aaron R. Gruber and Paul W. Berning

The general rule is that subcontractors providing bids to a general contractor must perform the work contemplated by their bids for the price quoted if the general contractor is chosen to perform the work. This rule is grounded in the doctrine of promissory estoppel and is followed in most jurisdictions.

One of the most widely cited cases on the issue is Drennan v. Star Paving Co., 51 Cal.2d 409 (1958). Drennan held that a subcontractor, which provided a bid by telephone, had to compensate a general contractor that relied on the bid for the additional cost of a replacement subcontractor after the original subcontractor refused to perform, claiming its bid contained a mistake. That is, the general contractor, which in good faith detrimentally relied on the price quote from the subcontractor by contractually binding itself to an owner, could rely on the sub's price, even before they signed a subcontract. Typical damages for failure to honor a bid are the difference between the original bid price and the cost of a replacement contractor.

Four recent cases, however, show that this rule is not ironclad, especially when pricing or other essential terms are left open at the time of bidding or if the bid is not timely accepted.

In two of the cases, subcontractors were excused from their bids when general contractors sought to include schedule requirements in the subcontracts. Rouse Construction Co. v. Interstate Steel Corp., 2002 WL 54182 (Tenn. Ct. App. 2002); Lichtenberg Construction & Development, Inc. v. Paul W. Wilson, Inc., 2001 WL 1141236 (Ohio Ct. App. 2001). In the third, the general contractor failed to accept a bid within the 30-day time limit set out in the bid. Pickus Construction and Equipment v. American Overhead Door, 326 Ill.App.3d 518, 761 N.E.2d 356 (2002). In the fourth case, a subcontractor's insertion of disclaimer language regarding pricing in its bid proposal prevented the general contractor from enforcing the bid even though the subcontractor knew the general contractor would use the bid in making its own proposal to the owner. National Environmental Service Co. v. Ronan Engineering Co, 256 F3d 995 (10th Cir. 2001).


No Meeting of Minds on Schedule

In Rouse Construction, the Tennessee Court of Appeals held that a general contractor could not enforce a subcontractor's bid when the bid did not address the project's schedule. The subcontractor provided a bid for the fabrication and erection of steel for a church, and the general contractor relied on it. The bid did not include or commit to a schedule. After the general contractor was awarded the project, it began discussing scheduling with the subcontractor. It also presented for the first time a form of contract that would have exposed the subcontractor to liability for liquidated damages in an unspecified amount. The subcontractor proposed alternate schedules. After partial performance and unsuccessful negotiations lasting more than four months, the subcontractor declined to proceed further. The general contractor sued the subcontractor to enforce its bid.

The court held that scheduling was an essential term of the contract and that there was no meeting of the minds by the contractor and subcontractor on scheduling and liquidated damages so as to impose contractual or implied contractual liability. Indefiniteness as to an essential term can prevent formation of an enforceable contract, the court wrote. It noted that the form of contract proposed by the general contractor made time of the essence but also referred to "an agreed upon construction schedule." It found that partial performance in anticipation of a contract did not evidence a meeting of the minds. The court also held that the subcontractor could recover in quantum meruit for services and materials it provided to the project before negotiations broke down and it stopped work.


Strict Schedule Not Reasonably Expected by Sub

In Lichtenberg Construction, the court held that a general contractor could not enforce a masonry subcontractor's bid upon which it had relied when the bid was provided without knowledge of the contractor's schedule requirements. A "time-is-of-the-essence" clause in the proposed subcontract required the sub to complete the masonry work under "a strict time schedule" to allow for overall project completion by a specified date. The Ohio Court of Appeals set out the conditions for enforcing a bid:

[A] subcontractor is bound to its bid to a general contractor if the general contractor relied on that bid, was awarded a general contract, and notified the subcontractor within a reasonable time that the subcontractor's bid was accepted. But if the general contractor then proposes a subcontract with terms that the subcontractor should not reasonably have expected when the subcontractor made the bid, then the subcontractor will not be obligated to honor the bid.

The court noted that the strict time schedule was not included in the specifications the subcontractor reviewed before bidding. Thus, the court concluded, the subcontractor had no reason to expect that an inflexible time schedule would be included in the subcontract. If the time schedule for performance of the work had been included in the bid specifications, the court wrote, then the subcontractor would have been obligated to honor its bid.

Both the trial court and appellate court relied on testimony of an expert witness called by the masonry subcontractor to show that the scheduling requirement could not have been reasonably expected. The expert witness, himself a masonry subcontractor in the Cincinnati (Ohio) for 25 years, testified that although a "time-is-of-the-essence" clause was standard language in a subcontract, it "d [idn't] carry much weight" because in practice the general contractor and subcontractor negotiated the schedule in good faith. The expert also testified that if a general contractor was adamant that work be completed within a strictly limited time and refused to negotiate, then the subcontractor simply did not sign the contract. The expert testified that if a general contractor knew in advance that a strict time schedule was necessary for a project, it would send a letter of intent to the subcontractor requesting that it reserve a specific period of time in its schedule to work on the project.

The trial court determined that the standard of practice in the Cincinnati area, where the case arose, was for the subcontractor to offer a bid to the contractor, the contractor to accept the bid and the parties to negotiate the schedule. Instead, the contractor attempted to impose a strict, non-negotiable schedule on the subcontractor. The court determined that the subcontractor, when bidding, could not have reasonably expected the general contractor to require a strict schedule and, therefore, an enforceable agreement had not been reached between the parties when the general contractor accepted the subcontractor's bid.


Bid Not Accepted Within Time Limits

In Pickus Construction, a subcontractor ultimately demanded a price nearly twice its bid price for overhead doors. When the general contractor sued to enforce the bid, the subcontractor raised a number of defenses. The Appellate Court of Illinois rejected all but one: The bid's qualification that it was good for only 30 days because of potential price increases by suppliers and that a signed purchase order had to be tendered in that time. One was not so tendered.

To prevail on its claim of promissory estoppel, the court held, the general contractor had to prove: 1.) the defendant made an unambiguous promise; 2.) the plaintiff relied on the promise; 3.) the reliance was expected and foreseeable to one in the defendant's position; and 4.) the plaintiff's reliance on the promise was detrimental.

Because of the 30-day time limit on the bid, the court held, any reliance after the 30 days had run was not reasonable. It noted testimony by the subcontractor that the time limit was included because the sub's suppliers would hold their price quotes for only 30 days.

The court distinguished an earlier case cited by the general contractor. There, after the bid opening, the general contractor told the subcontractor that if it were awarded the contract, it would award the subcontract to the sub. At trial, the general contractor presented evidence establishing the existence of a trade practice that the conversation amounted to a contract award to the subcontractor. The court in Pickus Construction held that no evidence of a trade practice had been presented.

The outcome was particularly harsh for the general contractor. When the subcontractor submitted its bid, the general contractor contacted the sub to say the bid appeared to be erroneous. After reviewing its bid with the general contractor, the sub insisted that the bid was correct and refused to withdraw it from the plaintiff and other general contractors. The plaintiff general contractor explained to the sub that it would be at a competitive disadvantage if the sub did not withdraw the bid and the general contractor used a higher bid from another sub. Accordingly, the plaintiff general contractor informed the sub it would use the sub's bid and, if the plaintiff got the project, would make an award to the sub. The sub insisted that it would honor its bid.

After the general contractor was awarded the contract, the sub revealed that its bid was not based on the brand of doors set out in the owner's specifications but on purported "or equal" doors. The owner's architect twice refused to accept purported "or equal" doors proposed by the sub, leading the sub to nearly double its price as a condition of supplying the specified brand.


Price Quotation Was Heavily Qualified

In National Environmental Services, a subcontractor submitted a price quotation for equipment and installation of a leak detection system for fuel tanks. It provided: "The following quote is only a cursory view for budgetary purposes and the final components and costs are subject to change dependent on actual site conditions." Later, the general contractor, in writing, requested a "firm" price quote. The subcontractor then submitted a price quote but with substantially the same disclaimer language as before.

An employee of the general contractor testified that he paid little attention to the disclaimer because he had requested a "firm" price quote and because sufficient time had passed for the subcontractor to give more than "cursory" consideration to its pricing.

In the end, the contractor had to use another subcontractor, and the project was finished late and substantially over budget. At trial, the subcontractor asserted that no contract had been formed and that it had only engaged in prolonged negotiations with the general contractor. The jury found no contract was breached, and the Court of Appeals affirmed.


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.


Send This Report to a Colleague

Tools to Share, Organize, Comment on Information


©2003 ConstructionWebLinks, Inc.

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© ConstructionWebLinks, Inc.
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us