Construction Web guide: infrastructure, buildings, engineering, architecture
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us

Federal Preemption
Developer's Claim for Indemnity Against Architect for ADA and FHA Violations Rejected

Not Like Private Deals
City Contract May Not Be Modified Orally or by Course of Dealing, Court Holds

Business Risk Exclusion
CGL Insurer that Refused to Defend, Pay Claim Penalized, Held Liable

Little Known Hazard
Plumbers Burned as a Result of Natural Gas 'Odor Fade,' but Damage Award Reversed

Could Apply Broadly
Design Professional Denied Protection of Contract's Liability Limit by Florida Court

Part Of Lung Removed
Contractor Escapes Liability When Plaintiff Cannot Tie Infectious Fungus to Jobsite Dirt Stockpile

Disgorgement Order
Court Allows Discharge in Bankruptcy of Penalty for Violation of Contractor Licensing Law

Obligations Discharged
When Surety Takes Over Project, Owner Cannot Object to Replacement Contractor, Court Holds

Default Judgment
Notice, Accident, Own Work Defenses Rejected in Claims by General Contractor Against Plumber's Insurer

Previous Issues

Construction Industry News

Subcontractor May Use Total Cost Method in Miller Act Case


August 23, 2004


(A revised version of this article appears in The Construction Lawyer, Volume 24, No. 3, Summer 2004, published by the American Bar Association's Forum on the Construction Industry.)


Back to Industry Newsletters
By John W. Ralls

An electrical subcontractor claimed that it incurred extra labor and material costs of $110,641 on Jefferson Barracks in St. Louis. The subcontractor sued the prime contractor in U.S. District Court and included a Miller Act payment bond claim.

The subcontractor claimed the problems on the project were extreme. It noted that the project was scheduled for completion in six months but, because of delays caused by the federal government, took more than 22 months. The subcontractor sought to use the total cost method to calculate its damages.

The District Court permitted the subcontractor to present total cost damage evidence, but instructed the jury that the subcontractor had to prove, among other things, that the prime contractor had "some responsibility in causing [the subcontractor]'s actual losses." The subcontractor objected to this instruction because its case was premised on delays and disruptions caused by the government. The District Court overruled the subcontractor's objection, and the jury returned a verdict in favor of the prime contractor.

On appeal, the subcontractor argued that the jury instruction was in error because the Miller Act permits a subcontractor to recover its additional costs of labor and materials regardless of the fault of the general contractor. The prime contractor cited Nebraska Public Power District v. Austin Power, Inc., 773 F.2d 960 (8th Cir. 1985) to support its argument that when seeking to use the total cost method, a subcontractor must prove that the general contractor "had some responsibility in causing the subcontractor's losses."

The appellate court agreed with the subcontractor and reversed the District Court, concluding that "the total cost method can be used to calculate damages under the Miller Act, regardless of the fault of the general contractor," because "general contractors have privity of contract with the government and can thus recover delay damages directly from the government, while the subcontractors cannot." Lighting & Power Services, Inc. v. Roberts, 354 F.3d 817 (8th Cir. 2004).

The court distinguished Austin Power and other cases holding that to recover damages using the total cost method, a subcontractor must prove that the defendant is responsible for the subcontractor's loss. The court observed that these cases dealt with breach of contract claims, where the jury is required to find that the defendant is the "cause in fact" of the damages sustained by the subcontractor. The court distinguished these cases on the ground that under the Miller Act, the subcontractor need not prove that the general contractor was responsible for the subcontractor's losses and concluded the breach of contract cases had no applicability to a claim brought under the Miller Act. Subcontractors can recover delay damages under the Miller Act whether or not the general contractor is at fault.


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.


Send This Report to a Colleague

Tools to Share, Organize, Comment on Information


©2004 ConstructionWebLinks, Inc.

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© ConstructionWebLinks, Inc.
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us