 |
ConstructionWebLinks.com
In
the 1990s numerous prompt payment statutes were enacted
and amended in California. Two recent appellate court decisions
clarified several aspects of these laws, finding that:
| 1.
|
Unpaid
subcontractors are entitled to recover the 2 percent
a month prompt payment penalty on the unpaid sums
IN ADDITION TO prejudgment interest (typically 10
percent a year).
|
| 2.
|
A
contractor can avoid liability for prompt payment penalties
and attorney fees, even if the subcontractor ultimately
recovers money from the contractor, by showing the existence
of a "bona fide dispute" with the subcontractor.
|
| 3.
|
The
"disputed amount" of withheld funds is to
be determined at the time the funds are withheld, not
by reference to the amount the contractor contends is
in dispute at the time of trial.
|
In
first case, a contractor on a public school project received
the final progress payment, less retention, and then failed
to pay a subcontractor the $31,520 progress payment that
was admittedly due under the subcontract within the required
10 days. Morton Engineering & Construction, Inc.
v. Stanley Douglas Patscheck, 87 Cal.App.4th 712 (2001)
The reason for non-payment is not clearly stated in the
opinion but apparently was due to problems caused by a subcontractor
to the subcontractor. After the contractor was paid the
retention, he offered the subcontractor $42,800 as full
and final settlement of all claims on the project. This
sum represented the amount that the contractor admitted
was due under the contract but excluded extra work, interest
and penalties. Apparently the contractor never made any
further payments to the subcontractor. At trial, the subcontractor
recovered $111,316.73, which included the contract balance,
extra work, interest, penalties, attorney fees and costs.
On
appeal, the court focused on the provisions in Business
and Professions Code §7108.5, which provides (for both
public and private projects) that upon receipt of a progress
payment, the contractor must pay any subcontractor within
10 days the amount allowed the contractor for work performed
by the subcontractor. The contractor may withhold up to
150 percent of any amount over which a "good faith"
dispute exists. A violation of the statute entitles the
subcontractor to recover a penalty of 2 percent a month
on the outstanding balance payable. In the event that a
legal action is brought, the prevailing party is entitled
to recover attorney fees and costs.
The
appellate court rejected the contractor's argument that
allowing recovery of prejudgment interest (Civil Code §3287)
and the 2 percent penalty (Business and Professions Code
§7108.5) would result in a double recovery for the
subcontractor. The court, in holding that the subcontractor
could recover both, noted that Public Contract Code §7107,
a prompt payment statute for retention payments to contractors
and subcontractors on public projects, expressly states
that the 2 percent penalty is "in lieu of any interest
otherwise due," language not found in §7108.5.
In
the second case, a contractor withheld the subcontractor's
retention of $101,580.45 based on a dispute about the levelness
tolerances of a concrete floor installed by the subcontractor
in a cold storage facility. The trial court, in interpreting
the different contract provisions regarding the tolerances
for the concrete floor, held that
[T]here was no meeting of the minds between plaintiff
and defendant as to what the contractual specification
was for the suspended dock floor. Therefore, the plaintiff
did not breach the contract by failing to perform to the
defendant's interpretation
As such, it cannot be
said that the plaintiff or defendant breached the contract.
The
trial court found that both parties' interpretation of the
contract was reasonable and further found that the floor
met an industry standards tolerance. Ultimately, the trial
court awarded the subcontractor the full amount of the withheld
retention but refused to award a penalty and attorney fees
under Civil Code §3260 (prompt payment of retention
to contractors and subcontractors on private projects).
On
appeal, the subcontractor argued that it was entitled to
recover the penalty and attorney fees because §3260
essentially allows any subcontractor that sues and recovers
retention money to also recover its attorney fees. In other
words, §3260 provides for an award of attorney fees
to the party entitled to retention without regard to whether
or not a bona fide dispute existed.
The
Court of Appeals rejected this argument, stating that "attorney's
fees are to be awarded only in cases in which the retention
payments are not made within the required time periods,
i.e., where a bona fide dispute does not exist," and
that "the 2 percent penalty and attorney's fees are
directed at the more egregious situation in which a contractor
withholds payment of retention proceeds beyond specified
time periods and without cause." Denver D. Darling,
Inc. v. Controlled Environments Construction, Inc.,
89 Cal.App.4th 1221 (2001).
However,
the Court of Appeal found that the subcontractor was entitled
to recover the penalty and attorney fees because the contractor
withheld more than "150 percent of the disputed amount"
as provided in §3260. The evidence indicated that the
contractor had written to the subcontractor in February
1998 and represented that it had estimated the cost of corrective
work in June 1997 to be $32,394. The contractor withheld
the entire $101,580 retention, more than 150 percent of
the estimated cost of corrective work. At trial, the contractor
contended the corrective work would cost $200,000 to $300,000.
The
Court of Appeals held that the "disputed amount"
in §3260 refers to the amount in dispute at the time
the retention proceeds are withheld, which in the case of
payments to the subcontractors is 10 days after the contractor
receives the retention payments from the owner. It stated:
"Any sums withheld in excess of 150 percent of the
'estimated value of the disputed amount' are thus not subject
to a bona fide dispute, and are 'improperly withheld' beyond
the applicable time period." In such a case, the prevailing
party is entitled to recover its attorney fees. The Darling
court remanded to the trial court the issue of entitlement
to attorney fees and, presumably, the 2 percent a month
penalty.
While
these cases provide important clarifications of the prompt
payment laws, they also underscore the critical importance
of proper and thorough documentation by the contractor when
it makes a decision not to pass through a progress or retention
payment to the subcontractor. The penalties if the contractor
is unable to establish its "good faith" or a "bona
fide" dispute are a whopping 34 percent a year (2 percent
a month plus statutory interest of 10 percent a year) plus
payment of the attorney fees and costs for both sides. On
the positive side for general contractors, the reasoning
of the Morton and Darling decisions applies
with equal force to payments by owners to contractors, making
the 34 percent and attorney fees recoverable by the contractor
from the owner when an owner violates the prompt payment
statutes.
If you would like to receive legal reports and updates
more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.
©2001 ConstructionWebLinks, Inc.
|