|
By
John R. Heisse II Howrey LLP
Public
projects are governed by strict statutory and regulatory
frameworks intended to reduce the risk of fraud, favoritism
and undue influence and to reassure taxpayers that their
tax dollars are being spent properly. In recent years, "best
value" procurement has begun to encroach upon traditional
procurement methods at both the state and federal level.
The federal government is increasingly using "best
value" procurement for its acquisitions. Approximately
half the states have some type of "best value"
procurement. 1/ Last year, the ABA Model Procurement
Code added design-build procurement as a new project delivery
method to assist state and local agencies in implementing
"best value" procurement. 2/ The
shift to best value models permits government agencies to
operate more efficiently. The ultimate goal of best value
procurement methods is to combine the twin goals of promoting
efficiency of private construction contracting and taxpayer
trust in the procurement process.
Historically,
public projects used traditional design-bid-build procurement.
The design-bid-build method requires separate contracts
between the owner and designer on the one hand and the owner
and constructor on the other. Contracts are awarded to the
lowest responsible bidder. Statutory bond requirements allay
concerns about the ability of the low bidder to perform
the project. Payment and performance bonds guarantee that
subcontractors will be paid and the work will be performed
as promised. However, the traditional design-bid-build model
does not allow the government to evaluate contractor bids
based on factors other than price. Other concerns that could
dramatically change the evaluation process include completing
the project in the shortest amount of time, incorporating
necessary aesthetic or environmental design issues, and
producing a facility with the lowest long-term operating
and maintenance costs. 3/
Although
the programs differ greatly, best value procurement generally
permits flexibility not offered by traditional competitive
bidding. In a design-build project, the owner contracts
with only one entity: the designer-builder. Design-build
not only offers single source responsibility, it decreases
adversarial communication between the parties working on
the project, promises quicker project completion, allows
single source responsibility, provides greater ability to
consider the past performance records of bidders, and typically
reduces administrative costs.
I. Federal Construction Contracting
Best
value procurement was introduced to the federal acquisition
system through legislative and regulatory initiatives. The
Clinger-Cohen Act of 1996 enacted design-build procurement
for the federal government. 4/ The Act describes
the two-phase selection procedure and the concept of "efficient
competition." 5/ The Act defines "efficient
competition" as a balance between the need "to
obtain full and open competition" and "the need
to efficiently fulfill the Government's requirements."
6/ The statute codifies the design-build construction
method popular in the private sector. The Federal Acquisition
Regulation (FAR) implements the Clinger-Cohen Act and the
two-phase design-build process for federal procurement.
7/
However,
the statutes and regulations provide only a procedure to
use best value procurement; they do not require an agency
to use best value procurement. 8/ The two-phase
procedures "are generally appropriate for unusual or
complex projects for which technical competence and demonstrated
past performance are critical." 9/ If
the government agency determines the two-phase design-build
procedure is appropriate for its project, it must create
a "scope of work" statement that "defines
the project and states the Government's requirements."
10/
A. Two-Phase Procedure
In
Phase 1, the government narrows the field of potential bidders
to a short list of no more than five of the best qualified
design-build contractors without looking at price. During
Phase 2, the government selects the design-build contractor
who provides the "best value" based on all appropriate
factors, including price.
1. Phase 1
After
the agency determines that design-build procedures are appropriate
and creates the scope of work statement, it issues a solicitation.
11/ The solicitation incorporates the scope
of work statement along with the evaluation factors the
agency will consider. 12/ These factors include
specialized experience and technical competence, capability
to perform, past performance of the offeror's team (including
the architect-engineer and construction members), other
appropriate factors (excluding cost or price-related factors,
which are not permitted in Phase 1). 13/ Importantly,
Phase 1 does not include detailed design or pricing information.
Nor do the regulations limit the discussions the government
may have with offerors during the selection of the short
list. 14/
The
explicit exclusion of cost or price data from Phase 1 sets
the design-build procedure apart from the traditional competitive
process. By excluding cost or price data, the design-build
method permits agencies to focus on other important aspects
of bid proposals. The offeror is able to focus on the design
quality and technical requirements of a complex project
without regard to price. 15/ During this phase,
the government may evaluate the proposals without fear that
the competitors simply are trying to under-bid each other
regardless of the impact on the project. 16/ Furthermore,
the offeror benefits from the reduced proposal preparation
expenses because it does not have to produce a detailed
cost analysis unless it is selected to enter Phase 2. 17/
The
FAR defines past performance information as:
relevant
information for future source selection purposes, regarding
a contractor's action under previously awarded contracts.
It includes, for example, the contractor's record of conforming
to contract requirements and to standards of good workmanship;
the contractor's record of forecasting and controlling
costs; the contractor's adherence to contract schedules,
including the administrative aspects of performance; the
contractor's history of reasonable and cooperative behavior
and commitment to customer satisfaction; and generally,
the contractor's business-like concern for the interest
of the customer. 18/
The
FAR definition is subjective and permits the government
agency to exercise broad discretion. 19/ Thus,
" 'the government has wide latitude in establishing
a contractor's performance rating.' " 20/ The
burden is on the government agency to maintain information
on contractor past performance and prepare a past performance
evaluation report for each competing contractor. 21/
However, contractors are permitted to "submit
comments, rebutting statements, or additional information"
relating to the evaluation. 22/ In the event
of a disagreement, discrepancies are resolved "at a
level above the contracting officer." 23/ Ultimately,
the contracting agency retains the final decision regarding
content of the past performance evaluation. 24/ Finally,
the solicitations must describe the approach for evaluating
past performance information, including how the agency will
evaluate offers when no past performance information is
available. 25/ General Accounting Office decisions
indicate that when there is a lack of past performance information,
"the offeror may not be evaluated favorably or unfavorably
on past performance." 26/
Phase
1 narrows the field of offerors based primarily on technical
competence and past performance. The result is a short list
of contractors best qualified to compete in Phase 2. 27/
Generally, this short list is limited to five contractors.
28/ The list may include more than five contractors
only if the greater number of competitors is in "the
Government's interest and is consistent with the purposes
and objectives of two-phase design-build contracting."
29/ This short list will thus include only
those competitors likely to provide "best value"
to the government.
2. Phase 2
After
the agency creates the short list, the competitors must
comply with the solicitation requirements for Phase 2. The
solicitation may be issued concurrently with the Phase 1
solicitation or after creation of the short list. 30/
The Phase 2 solicitation "shall require submission
of technical and price proposals, which shall be evaluated
separately, in accordance with Part 15." 31/
The agency must indicate in the solicitation all factors
to be considered and their relative importance. 32/
After the 1997 revisions to FAR Part 15, the government
has significant discretion and flexibility during the two-phase
process. The regulations require that competitors "shall
be treated fairly and impartially but need not be treated
the same." 33/ One recent analysis of
the current FAR regulations for Phase 2 noted "[t]he
rewrite encourages presolicitation conferences, one-on-one
meetings, and even draft requests for proposals concerning
future contracting opportunities." 34/
FAR
Part 15 also permits the government to negotiate with competitors
to achieve "best value." 35/ FAR
§15.306 (d) defines negotiation or bargaining as "persuasion,
alteration of assumptions and positions, give and take,
and may apply to price, schedule, technical requirements,
type of contract, or other terms of a proposed contract."
36/ The government may also:
[N]egotiate
with offerors for increased performance beyond any mandatory
minimums, and the Government may suggest to offerors that
have exceeded any mandatory minimums (in ways that are not
integral to the design), that their proposals would be more
competitive if the excesses were removed and the offered
price decreased. 37/
Finally,
each offeror has the opportunity to revise its proposal
during the negotiations and to submit a "final proposal
revision." 38/ However, the regulations
prohibit conduct that favors one offeror over another, that
reveals an offeror's technical solution, or that reveals
an offeror's price without that offeror's permission. 39/
These regulations give government agencies "considerable
discretion" in the procurement process. 40/
During
Phase 2, the evaluating agency may consider cost information.
41/ The best value procurement method permits
the agency to "conduct a price/technical trade-off
analysis of an offeror's technical proposal and prices in
order to determine which proposal is most advantageous to
the government" and, thus, "make an award to a
higher priced offeror that has submitted a technically superior
offer." 42/
II. State Construction Contracting
Many
states are enacting legislation to explicitly permit best
value procurement while statutes in other states are amenable
to best value procurement. 43/ State laws generally
fall into four categories:
1. "laws that expressly prohibit design-build"
2. "laws that pose obstacles to design-build"
3. "laws that pose no obstacles to design-build"
4. "laws that expressly allow design-build."
44/
In
the states the permit or encourage best value procurement,
the names used to describe this method include "performance-based
procurement," 45/ "innovative procurement,"
46/ "competitive best value bidding," 47/
"competitive selection" 48/ and "competitive
negotiation." 49/ Like the names, the actual
methods vary greatly in evaluation factors and in general
procedure. 50/ In some states, the agencies are required
to delineate the pertinent factors; other states establish
uniform criteria for all best value procurement; still other
states combine both approaches. However, like the federal
design-build process, most states employ a two-phase procedure
for best value procurement. 51/ This section
presents the applicable law from selected jurisdictions.
A. California
California
law permits the use of design-build for public projects,
but only with specific authorization from the Legislature.
52/ The Legislature found:
[T]hat
the design-build process can be an attractive option to
the Department of General Services in comparison to the
existing three-step (design-bid-build) process. The design-build
process can improve the project delivery process by accelerating
delivery schedules and saving costs by promoting improved
coordination between contractor and architect, shifting
management risk from the state to the design-build team,
and minimizing change orders through early collaboration
between design and construction disciplines. 53/
Design-build
has been authorized as an alternative bidding procedure
for the several counties 54/ and for transit projects.
55/ The many California design-build procurement
statutes give detailed considerations for design-build projects.
56/ For example, in the procedures guiding the procurement
of state office facilities, the Legislature requires that
bidders meet strict prequalification standards:
| |
(i) |
Possession
of all required licenses, registration and credentials
in good standing that are required to design and construct
the project. |
| |
|
|
| |
(ii) |
Submission
of evidence that establishes that the design-build entity
members have completed, or demonstrated the capability
to complete, projects of similar size, scope or complexity
and that proposed key personnel have sufficient experience
and training to competently manage and complete the
design and construction of the project. |
| |
|
|
| |
(iii) |
Submission
of a proposed project management plan that establishes
that the design-build entity has the experience, competence
and capacity needed to effectively complete the project. |
| |
|
|
| |
(iv) |
Submission
of evidence establishing that the design-build entity
has the capacity to obtain all required payment and
performance bonding, liability insurance, and errors
and omission insurance, as well as a financial statement
that assures the department that the design-build entity
has the capacity to complete the project. |
| |
|
|
| |
(v) |
Provision
of a declaration certifying that members of the design-build
entity have not had a surety company finish work on
any project within the last five years. |
| |
|
|
| |
(vi) |
Provision
of information and a declaration providing detail concerning
all of the following: |
| |
|
|
|
| |
|
(1) |
Any
construction or design claim or litigation totaling
more than $500,000 or 5 percent of the annual value
of work performed, whichever is less, settled against
any member of the design-build entity over the last
five years. |
| |
|
|
|
| |
|
(2) |
Serious
violations of the Occupational Safety and Health Act
as provided in Part 1 (commencing with Section 6300)
of Division 5 of the Labor Code settled against any
member of the design-build entity. |
| |
|
|
|
| |
|
(3) |
Violations
of federal or state law, including, but not limited
to, those laws governing the payment of wages, benefits,
or personal income tax withholding or Federal Insurance
Contributions Act (FICA) withholding requirements, state
disability insurance withholding or unemployment insurance
payment requirements, settled against any member of
the design-build entity over the last five years. |
| |
|
|
|
| |
|
(4) |
Information
required by Section 10162 of the Public Contract Code
(regarding the bidder's prior disqualification or removal
from bidding or completing public work). |
| |
|
|
|
| |
|
(5) |
Violations
of the Contractors' State License Law (Chapter 9) (commencing
with Section 7000 of Division 3 of the Business and
Professions Code) excluding alleged violations or complaints.
|
| |
|
|
|
| |
|
(6) |
Any
conviction of any member of the design-build entity
of submitting a false or fraudulent claim to a public
agency over the last five years. |
| |
|
|
|
| |
|
(7) |
Provision
of a declaration that the design-build entity will comply
with all other provisions of law applicable to the project,
including, but not limited to, the requirements of Chapter
1 (commencing with Section 1720) of Part 7 of Division
2 of the Labor Code. 57/ |
There
are no published cases either interpreting these sections
or regarding disputes arising from the use of the design-build
procurement method pursuant to these sections.
B. Florida
Florida
public contracting law permits the use of design-build contracts.
58/ However, each agency must implement its own procedures
for awarding design-build contracts within the statutory
guidelines. At the very minimum, each agency must:
| |
1. |
Have
a "design criteria professional" 59/
prepare a "design criteria package" (i.e.,
"concise, performance-oriented drawings or specifications").
60/ |
| |
|
|
| |
2. |
At
least three firms must be selected for the second phase
of evaluation based on qualifications, availability
and past work. |
| |
|
|
| |
3. |
The
agency must establish criteria, procedures and standards
for evaluation. |
| |
|
|
| |
4. |
Competitive
proposals must be solicited based on the design criteria
package. |
| |
|
|
| |
5. |
Have
the design criteria professional evaluate the responsiveness
of the bids. |
| |
|
|
| |
6. |
Establish
procedures to authorize negotiations with the best qualified
available firm in the event of an emergency. 61/
|
C.
Massachusetts
Massachusetts
law permits state agencies to consider design-build as an
alternative to traditional bidding methods. 62/ However,
as a recent case indicates, even when design-build is not
specified as a possibility, the contracting agency may use
best value considerations generally. 63/ In
J.F. White Contracting Co. v Massachusetts Port Authority,
the court determined that the statute governing the award
of construction contracts generally contains no language
prohibiting "alternative bidding procedures."
64/ Furthermore, the bid procedures in question
did not violate any public policy concerns about fair competition
or notice because the bid solicitation documents fully explained
and defined the requirements for both alternatives. 65/
However, neither the statute explicitly authorizing
the consideration of design-build methods, nor recent case
law provide any guidelines for an agency wishing to use
this procurement method.
D. South Carolina
South
Carolina explicitly permits "competitive best value
bidding." However, cost of the proposal must be a factor
in determining the award and cannot be weighted at less
than 60 percent of the numerical weighting of all factors.
66/ The statute also provides that the agency
may evaluate contracts by using the following subjective
factors:
(a)
operational costs that the state would incur if the bid
is accepted; (b) quality of the product or service
or its technical competency; (c) reliability of
delivery and implementation schedules; (d) maximum
facilitation of data exchange and system integration;
(e) warranties, guarantees and return policy;
(f) vendor financial stability; (g) consistency
of the proposed solution with the state's planning documents
and announced strategic program direction; (h)
quality and effectiveness of business solution and approach;
(i) industry and program experience; (j)
prior record of vendor performance; (k) vendor
expertise with engagements of similar scope and complexity;
(l) extent and quality of the proposed participation
and acceptance by all user groups; (m) proven development
methodologies and tools; and (n) innovative use
of current technologies and quality results. 67/
These
requirements have not resulted in any published cases. This
leaves room for speculation regarding whether this is a
result of the successful functioning of this statute or
whether it is due to a lack of use caused by the complexity.
E. Texas
Changes
to Texas statutes effective September 1, 2001, greatly expand
best value procurement 68/ and added procedures for
design-build contracting. 69/ If a municipality
decides to use best value procurement, it must state in
the bid specifications that the bid may be awarded to the
bidder who provides the best value. 70/ Best
value "may" be evaluated by using: the purchase
price, the reputation of the bidder and the bidder's goods
or services, the quality of the bidder 's goods or services,
the extent to which the goods or services meet the governmental
entity's needs, the bidder 's past relationship with the
governmental entity, the impact on the ability of the governmental
entity to comply with laws and rules relating to historically
underutilized businesses, the total long-term cost to the
governmental entity to acquire the bidder's goods or services,
and any other relevant factor that a private business entity
would consider in selecting a bidder. 71/ The
requirements apply to state agencies, districts, authorities,
counties, municipalities, other political subdivision or
any entity created by or acting on behalf of a political
subdivision. 72/ However, the changes explicitly
prohibit the use of best value procurement methods for "highways,
roads, streets, bridges, utilities, water supply projects,
water plants, wastewater plants, water and wastewater distribution
or conveyance facilities, wharves, docks, airport runways
and taxiways, drainage projects, or related types of projects
associated with civil engineering construction." 73/
The
new design-build procedures implement a two-phase process
for evaluating bids. In Phase 1 the agency may consider
"offeror's experience, technical competence, and capability
to perform, the past performance of the offeror's team and
members of the team, and other appropriate factors submitted
by the team or firm in response to the request for qualifications,
except that cost-related or price-related evaluation factors
are not permitted." 74/ Phase 2 requires
the entity to use the selection criteria stated in the request
and based on the results of any interviews. However, the
entity "may request additional information regarding
demonstrated competence and qualifications, considerations
of the safety and long-term durability of the project, the
feasibility of implementing the project as proposed, the
ability of the offeror to meet schedules, costing methodology,
or other factors as appropriate." 75/
F. Washington
Washington
also recently revised its design-build statutes. 76/
Previous design-build statutes were effective only
until July 2001. 77/ The Legislature explicitly
stated that design-build may be used for public works projects
valued at more than $12 million if the construction technology
is highly specialized, the project design is repetitive,
or regular interaction with facilities users and operators
is not critical to effective design. 78/ The
process also may be used for pre-engineered or prefabricated
buildings or student housing projects valued at more than
$5 million. 79/ The evaluation factors "shall"
include: "proposal price; ability of professional personnel;
past performance on similar projects; ability to meet time
and budget requirements; ability to provide a performance
and payment bond for the project; recent, current and projected
workloads of the firm; location; and the concept of the
proposal." 80/ The Washington statute
is unusual because it requires that the listed factors "shall"
be taken into consideration. 81/ The statute
provides that the bids shall be evaluated by committee,
and the committee will select three to five proposals for
a second phase of evaluation. 82/
III. Conclusion
Critics
of design-build or any type of "best value" procurement
in the public sector question whether the discretion required
of the government agency violates public policy. Federal
laws mandate fair and equal treatment of bid competitors
83/ and require full and open competition. 84/
During congressional debates on "efficient competition,"
Rep. Cardiss Collins (D. Ill.) argued that "emphasizing
subjectivity in awarding contracts creates a breeding ground
for prejudice because [contracting officers], given the
choice, will usually go with a well-established large firm
instead of a small business offering a lower price."
85/ The use of efficient competition to limit
the number of competitors in Phase 2 "may exclude smaller
or less experienced contractors although they are fully
capable of meeting the government's needs and may provide
a lower price." 86/
Concerns
also exist about the use of best value procurement at the
state level. However, the variety and complexity of state
best value procurement procedures make it difficult to generalize
about the benefits and drawbacks. One recent article noted
the process "is more labor intensive for the procuring
agency or its designated consultants, can give rise to procedural
errors by contracting officers and evaluators, requires
more "business judgment" by the evaluators, and
can lead to abuse of discretion without the protections
normally available with procurement awards based on low
price." 87/ Also, despite the benefits
of single-point responsibility, one drawback may be that
the owner may lose the ability to obtain access to information
that it would ordinarily have on the traditional design-bid-build
project because of the communication required between designer
and builder. 88/ The use of subjective selection
criteria could create the possibility for abuse of discretion
in determining the meanings of "quality," "value,"
"past performance" and other requirements. 89/
However,
the federal regulations strike a balance between full and
open competition and the need increase efficiency in government
contracting. 90/ Although the competition may
inhibit the ability of smaller firms to compete, market
forces should compensate as "firms form suitable joint
ventures or other partnering arrangements." 91/
In addition, the two-phase process is cost effective
both for competitors and for the government agency. 92/
Although the balance may not be perfect, the current
federal regulations bring contracting in the public sector
closer to the efficiency enjoyed by the private sector.
Only time and increased use will show whether the design-build
method and the best value procurement generally will meet
the goal of reducing litigation in public contracting.
If you would like to receive legal reports and updates quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.
For more information about the issues covered in this report, please contact John R. Heisse II in our San Francisco office at 415-848-4943 or at heissej@howrey.com or contact your Howrey attorney. For more information about Howrey's Construction Practice Group, click here.
ENDNOTES
1/ Jesse B. Grove, III, Risk Allocation From the
Contractor's Perspective: Philosophies of Risk Allocation,
N-467 Real Estate Law and Practice 41, 63 (PLI 2001).
2/
2000 ABA Model Procurement Code, Article 5, "Procurement
of Infrastructure Facilities and Services."
3/
Grove, supra n. 1, at 63-64.
4/
Pub. L. No. 104-106, §4001, 110 Stat. 186, 642.
5/
10 USC §2304 (j).
6/
Id.
7/
48 CFR §15.000; 48 CFR §36.000.
8/
48 CFR §36.3; 10 USC §2305a (b).
9/
Kurt A. Didier, Construction Contracting and the New
Two-Phase Design Build Selection Procedures: Balancing Efficiency
with a Full and Open Competition, 27 Pub. Cont. L.J.
589, 601 (1998).
10/
48 CFR §36.302.
11/
48 CFR §36.303; 48 CFR §36.303-1.
12/
48 CFR §36.303-1.
13/
48 CFR §36.303-1.
14/
48 CFR §36.303-1 (b).
15/
Didier, supra n. 9, at 605.
16/
Id.
17/
Id.
18/
48 CFR §42.1501.
19/
48 CFR §42.1503 (a).
20/
Robert S. Brams, Michael J. Schaengold and Rodney A. Grandon,
Best Value in Federal Construction Contracting, 19:2
Constr. Law. 25, 27 (April 1999), quoting Adrian
L. Bastianelli, III, George W. Stiffler and Lori Ann Lange,
New Federal Regulations Affecting the Construction Industry,
Construction Briefings, Second Series, No. 98-4 (March 1998).
21/
48 CFR §§42.1500 to 42.1503.
22/
48 CFR §42.1503.
23/
48 CFR §42.1503.
24/
48 CFR §42.1503.
25/
48 CFR §15.305 (a) (2) (iv).
26/
Brams, Schaengold and Grandon, supra n. 20, at 27, citing
Braswell Services Group, Inc., B-278921.2, 98-2 CPD
§10 [agency properly assigned a "satisfactory"
past performance rating to offeror for whom no relevant
past performance information was available; agency regarded
"satisfactory" rating as an average evaluation
with no major strengths or weaknesses].
27/
10 USC §2305a (c) (2).
28/
10 USC §§2305a (c) (4) to 2305a (d).
29/
48 CFR §36.303-1 (a) (4).
30/
48 CFR §36.303.
31/
48 CFR §36.303-2 (b).
32/
48 CFR §15.304; 10 USC §2305 (a) (2) (A) (i);
41 USC §253a (b) (1) (A).
33/
48 CFR §1.102-2 (c) (3).
34/
Brams, Schaengold and Grandon, supra n. 20, at 28;
FAR §15.201 (c); FAR §15.201 (f).
35/
48 CFR §15.306 (d).
36/
Id.
37/
48 CFR §15.306 (d) (3).
38/
48 CFR §15.307 (b).
39/
48 CFR §15.306 (e).
40/
Brams, Schaengold and Grandon, supra n. 20, at 29,
citing Telos Corp., B-279493.3, 98-2 CPD §1,
8.
41/
48 CFR §15.305 (a) (4).
42/
Brams, Schaengold and Grandon, supra n. 20, at 29;
48 CFR §15.101-1; 48 CFR §15.305 (a) (4).
43/
For comprehensive analysis of state best value procurement,
see generally, The Design/Build Deskbook, 2nd ed.
(John R. Heisse, II, editor); Kenneth M. Roberts and Nancy
C. Smith, Design-Build Contracts Under State and Local
Procurement Laws, 25 Pub. Cont. L.J. 645 (1996).
44/
Roberts and Smith, supra n. 42, at 647.
45/
OFFP Policy Letter 91-2 (April 9, 1991).
46/
Alaska Statute §36.30.308.
47/
South Carolina Code Annotated §11-35-1528.
48/
Florida Statutes Annotated §287.055 (4).
49/
Kentucky Revised Statutes §45A.085; see generally,
Dean B. Thomson and Michael J. Kinzer, Best Value in
State Construction Contracting, 19:2 Constr. Law. 31
(April 1999).
50/
Thomson and Kinzer, supra n. 48, at 31; Roberts and
Smith, supra n. 42, at 646-47.
51/
Thomson and Kinzer, supra n. 48, at 33.
52/
Section 1 (b) of Stats. 1998, ch. 252 §1 (S.B. 776).
53/
Id.
54/
California Public Contract Code §20133 (a) (1).
55/
California Public Contract Code §20209.6.
56/
California Public Contract Code §§14661, 20133,
20209.6 to 20209.8.
57/
California Government Code §14661 (d) (2) (B).
58/
Florida Statutes Annotated §287.055.
59/
Defined as a registered architect or engineer employed by
or under contract with the agency to provide architectural
or engineering services. Florida Statutes Annotated §287.055
(2) (k).
60/
Id. at §287.055 (2) (j).
61/
Florida Statutes Annotated §§287.055 (10) (b)
and 287.055 (10) (c).
62/
Massachusetts General Laws Annotated, ch. 29, 7E; Id.
ch. 7, 42B; Id. ch. 149, 44A.
63/
J.F. White Contracting Co. v. Massachusetts Port Authority,
748 N.E. 2d 1020, 1024 (Mass. App. Ct. 2001).
64/
Id.
65/
Id.
66/
South Carolina Code Annotated §11-35-1528 (5).
67/
South Carolina Code Annotated §§11-35-1528
(5) (a) to 11-35-1528 (5) (n).
68/
2001 Texas Advance Legislative Service 1409 (SB 510).
69/
2001 Texas Advance Legislative Service 1422 (SB 311).
70/
2001 Texas Advance Legislative Service 1409 (SB 510).
71/
2001 Texas Advance Legislative Service 1409 (SB 510).
72/
Id.
73/
Id.
74/
2001 Texas Advance Legislative Service 1422 (SB 311).
75/
2001 Texas Advance Legislative Service 1422 (SB 311).
76/
2001 Washington Advance Legislative Service 328 (SB
5060); 2001 Washington Advance Legislative Service 226 (HB
1680).
77/
Revised Code Wash. §39.10.
78/
2001 Washington Advance Legislative Service 328 (SB
5060).
79/
Id.
80/
Id.
81/
Thomson and Kinzer, supra n. 48, at 32.
82/
2001 Washington Advance Legislative Service 328 (SB
5060).
83/
48 CFR §6.000.
84/
10 USC §2304; 41 USC §253.
85/
141 Congressional Record H8852-02, at H8869 (daily ed.
Sept. 13, 1995).
86/
Brams, Schaengold and Grandon, supra n. 20, at 26.
87/
Thomson and Kinzer, supra n. 48, at 33.
88/
Id. at 34.
89/
Id. at 34.
90/
Didier, supra n. 9, at 613.
91/
Id.
92/
Id.
©2002 Howrey LLP
|