Construction Web guide: infrastructure, buildings, engineering, architecture
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us

Federal Preemption
Developer's Claim for Indemnity Against Architect for ADA and FHA Violations Rejected

Not Like Private Deals
City Contract May Not Be Modified Orally or by Course of Dealing, Court Holds

Business Risk Exclusion
CGL Insurer that Refused to Defend, Pay Claim Penalized, Held Liable

Little Known Hazard
Plumbers Burned as a Result of Natural Gas 'Odor Fade,' but Damage Award Reversed

Could Apply Broadly
Design Professional Denied Protection of Contract's Liability Limit by Florida Court

Part Of Lung Removed
Contractor Escapes Liability When Plaintiff Cannot Tie Infectious Fungus to Jobsite Dirt Stockpile

Disgorgement Order
Court Allows Discharge in Bankruptcy of Penalty for Violation of Contractor Licensing Law

Obligations Discharged
When Surety Takes Over Project, Owner Cannot Object to Replacement Contractor, Court Holds

Default Judgment
Notice, Accident, Own Work Defenses Rejected in Claims by General Contractor Against Plumber's Insurer

Previous Issues

Construction Industry News

Void Contract Rule Does Not Require Refund of Change Order Payments Made to South Dakota Public Works Contractor


April 22, 2002


Back to Industry Newsletters
 

(A revised version of this article appears in The Construction Lawyer, Volume 22, No. 2, Spring 2002, published by the American Bar Association's Forum on the Construction Industry.)


By John W. Ralls

The City of Brookings, South Dakota, hired the low bidder to construct an exhibition hall and research building. During construction, the city issued two significant change orders: (1) A $107,000 change order for paving a parking lot originally scheduled to be gravel and (2) A $441,000 change order for tenant improvements of a portion of the building originally scheduled to be left unimproved. The two change orders were negotiated, not competitively bid.

The contractor inquired about the propriety of proceeding with the change orders without competitive bidding. The City Attorney opined that the change orders were permissible because the changes were precipitated by unforeseen circumstances necessary to the completion of the project. When the legality of the change orders was questioned by a taxpayer and found to be unlawful by a state auditor, the city adopted an ordinance allowing it to proceed even if the change orders were later found unlawful by a court.

The taxpayer sued the city and the contractor to have the change orders declared void and to have any payments to the contractor refunded. The trial court granted summary judgment in favor of the taxpayer and ordered that the contractor refund all amounts paid on the invalid change orders. The South Dakota Supreme Court affirmed in part and reversed in part. Bozied v. City of Brookings, 2001 S.D. 150, 638 N.W.2d 264 (2001). There were three parts to the court's opinion.

First, the Supreme Court found that the ordinance purporting to legalize the change orders was invalid. The city defended the ordinance on the ground it held a home rule charter that, under the South Dakota Constitution, permitted the city to "exercise any legislative power or perform any function not denied by its charter, the constitution or the general laws of the State." South Dakota Constitution, Article IX, §2. The South Dakota Supreme Court rejected this argument because home rule powers may not be exercised to establish standards or requirements that are lower or less stringent than those imposed by state law. Moreover, South Dakota Constitution Article XII, §3 provides that even the Legislature may not authorize payment of claims made under void contracts. The court also concluded that even if the ordinance were valid, it could not retroactively validate void contracts.

Second, the court considered whether the change orders should have been competitively bid. At the time the change orders were negotiated, South Dakota Codified Law §5-18-18.3 provided:

Any amendment or change order to an existing construction contract need not be bid if the contract contains unit prices for the same type or class of work, or the change or extra work is necessitated by circumstances not reasonably foreseeable at the time the underlying contract was let and the change or extra work is necessary to the completion of the project.

The South Dakota Legislature later amended SDCL §5-18-18.3 to limit the "reasonably foreseeable" exception to situations where the "change or extra work is necessitated by circumstances related to soils, utilities, or unknown conditions directly affecting the performance of the work…." The court applied the older version of the statute, which was in effect at the time the change orders were issued.

The contractor argued that what was "reasonably foreseeable" and what was "necessary" to complete the project were questions of fact. The contractor claimed that it was necessary to pave the parking lot and build out the space to accommodate new tenants, which had signed leases and wanted to move in sooner than had been reasonably foreseen. The court agreed that the issues could not be resolved by summary judgment and remanded the case for trial of those issues.

Third, the court grappled with what it said was the "crux of our case," whether the contractor was required to refund payments in the event the trier of fact found the change orders to be invalid. On the one hand, the court said that a harsh and inflexible rule that requires contractors to return money paid for a void contract promotes government integrity and public protection. On the other hand, the court said that such a rule may unfairly punish a contractor who performs in good faith and may unjustly enrich the public entity. After reviewing decisions from other states, the court found that "several courts faced with this situation have allowed a contractor to retain funds already paid but not to recover additional funds." The court concluded, "A contractor who fully performs a contract of this character and then receives payment should not be compelled to refund the money." In such situations, the courts should leave the parties where it finds them.

The taxpayer alleged that the city and the contractor had colluded. The taxpayer pointed to the fact that the contractor's principal had served on a design committee for the project and to the fact that the City Attorney was a law partner of the contractor's attorney. The court found the charges to be serious but unproven. "In the event the change orders are found to violate th[e] statute, the contractor may nonetheless retain all payments received in the absence of proof of fraud, collusion, or undue influence."

A dissenting justice argued that the change orders were void as a matter of law. The justice pointed out that the city foresaw the need to construct the tenant improvements and to pave the parking lot and that neither of these changes were necessary to the completion of the project that was let out to bid. "If City and [contractor] knew that these changes were going to be made at some point in the future, they were not unexpected and were reasonably foreseeable at the time the underlying contract was let." The dissenting justice also argued that the appropriate remedy for a void public contract was refund of the monies paid to the contractor. "The forfeiture of all the money paid under the illegal change orders may seem harsh in this instance; but I believe the remedy to the taxpayers is appropriate if the public bidding laws of the State of South Dakota are to have any real meaning in the future."


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.


Send This Report to a Colleague

Tools to Share, Organize, Comment on Information


©2002 ConstructionWebLinks, Inc.

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© ConstructionWebLinks, Inc.
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About CWL ConstructionWebLinks Contact Us